Cases / Project case study

Hong Kong International Airport — foundations across rock and reclamation

The original airport terminal crosses former island rock and newly reclaimed ground. The designer describes a range of foundation types adapted to these contrasting conditions; a contemporaneous paper documents vibrocompaction of marine sand fill.

Site investigationPiles and drilled shaftsShallow foundationsGround improvementSettlement and consolidation
Hong Kong International Airport at Chek Lap Kok viewed from the air.
Hong Kong International Airport at Chek Lap Kok viewed from the air. The photograph shows the actual airport platform; ground improvement and terminal foundation zones are documented separately.PSnyan · Image source · CC BY-SA 3.0

Project evidence

Design & engineering

Partial record

The sources describe actual foundation choices and field characterization. They do not provide a single uniform soil profile for the whole airport.

Sources: s1 · s2

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Not located in cited sources

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

Completion & performance

Not located in cited sources

Complete as-built drawings and acceptance records were not found in the reviewed sources.

Engineering methods

VibrocompactionCPT verificationMixed foundation systems

Suggested teaching exercise

Capstone project brief

Design the transition between a shallow foundation on rock and a piled concourse on reclaimed deposits.

Starting information & inputs

  • Distinguish original rock, weathered zones and reclaimed sand in a project ground model.
  • Extract the reported investigation and density-verification approach from the vibrocompaction paper.

Suggested deliverables

  • Compare settlement and construction risk for two terminal foundation zones.
  • Define CPT acceptance criteria and an interface detail for differential movement.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which discontinuity is more important: the former shoreline or the top of competent rock?
  • How can improvement verification avoid hiding local loose pockets behind an average density?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records