Cases / Project case study

ETH Hönggerberg — seasonal borehole heat storage

The campus anergy grid balances heating and cooling through buried borehole fields. Its documented HC4 expansion provides a practical study of thermal interference, drilling access and staged commissioning.

Ground-source energySite investigationDewatering and groundwaterMonitoring and observational designEstimating, sequencing and project delivery
The ETH Hönggerberg campus, where the anergy grid exchanges heat with borehole fields. This site-context photograph does not show the buried HC4 boreholes.
The ETH Hönggerberg campus, where the anergy grid exchanges heat with borehole fields. This site-context photograph does not show the buried HC4 boreholes.Balise42 / Wikimedia Commons · Image source · CC BY 4.0

Project evidence

Design & engineering

Partial record

ETH documents 160 additional probes at 200 m depth on a 5 m grid, beside an existing field of 126 probes. The published project description supports layout and heat-balance studies; it does not supply a complete thermal-response test dataset.

Sources: s1 · s2

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The owner dates HC4 expansion drilling to October 2024–May 2025 and operational handover to July 2025. Later proposed fields are outside this completed expansion.

Sources: s1 · s2

Completion & performance

Partial record

The owner confirms connection of the enlarged HC4 field to the campus network; continuous raw operating data and final drilling records were not provided on the reviewed pages.

Sources: s1 · s2

Engineering methods

Borehole heat exchangersSeasonal thermal storageThermal interferenceConstruction staging

Published quantities & cost references

These values retain the scope and date basis of their cited source. Estimates, alternatives and partial packages are identified individually.

Source-backed project quantities and costs
ItemReported valueScope & source
Added HC4 probes160 probesHC4 expansion drilled October 2024–May 2025.As reported by the cited project source; not a universal design input.Source s1 · HC4 expansion description
Reported probe depth200 mNew HC4 geothermal probes; do not infer the full site stratigraphy.As reported by the cited project source; not a universal design input.Source s1 · HC4 expansion description
Reported grid spacing5 mSpacing stated for the HC4 expansion.As reported by the cited project source; not a universal design input.Source s1 · HC4 expansion description
Existing HC4 probes126 probesPre-expansion field, distinct from the 160 additional probes.As reported by the cited project source; not a universal design input.Source s1 · HC4 expansion description

Suggested teaching exercise

Capstone project brief

Develop a phased borehole-field expansion for an operating campus and test whether spacing, ground properties and annual heat imbalance control the design.

Starting information & inputs

  • Use the published HC4 depth, spacing and probe counts; assemble an explicitly labelled study load series for heating and cooling.
  • Identify borehole logs, groundwater flow, thermal conductivity and borehole-resistance measurements still needed before design.

Suggested deliverables

  • Compare a line-source screening calculation with a multi-borehole response model under balanced and unbalanced annual loads.
  • Lay out drilling access, buried services, grouting verification, commissioning tests and long-term temperature monitoring.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • How would persistent net heat injection change performance even if the first operating year meets the heating and cooling demand?
  • What additional thermal-response or groundwater observations would justify reducing uncertainty at the 5 m borehole spacing?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records