I-70 Grizzly Creek — post-fire rockfall risk and betterment

After the 2020 fire, CDOT compared rockfall mitigation using risk and benefit-cost analysis. Subsequent debris flows exceeded some installed protection capacities.

Rock slopes and foundationsSoil slopes and landslidesScour and erosion protectionEstimating, sequencing and project delivery
Burn scars from the Grizzly Creek fire above I-70 in Glenwood Canyon, Colorado.
Burn scars from the Grizzly Creek fire above I-70 in Glenwood Canyon, Colorado. FHWA photograph from its rockfall and debris-flow mitigation case study.Federal Highway Administration (FHWA) · Image source · Public domain — U.S. federal government work

Project evidence

Design & engineering

Partial record

The FHWA case documents selected fence treatments, cost assumptions and the importance of distinguishing routine rockfall from larger debris-flow events.

Sources: s1

Cost & estimating

Partial record

The report lists a $2.692 million fence estimate and benefit-cost ratios for one- and five-year periods; other summary totals have different scopes.

Sources: s1

Schedule & construction

Partial record

Fences were installed in spring 2021; intense rainfall caused damaging debris flows in July 2021.

Sources: s1

Completion & performance

Partial record

The case records both reduced minor-rockfall disruption and damage during larger subsequent events.

Sources: s1

Engineering methods

Rockfall protectionRisk-based selectionBenefit-cost analysis

Suggested teaching exercise

Capstone project brief

Select a rockfall-protection strategy under changing post-fire hazard and explicitly describe the residual risk from events beyond its capacity.

Starting information & inputs

  • Extract the source cost table, hazard categories and analysis periods.
  • Verify energy units and fence specifications against design documents before using them; the summary’s unit labels require confirmation.

Suggested deliverables

  • Recalculate the published benefit-cost comparison with transparent assumptions.
  • Develop a fence layout concept, inspection triggers and a response to debris-flow exceedance.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.