FHWA / CDOT · 2023
public-link · US federal agency case study; original credits retained · Checked 2026-11-22I-70 Grizzly Creek — post-fire rockfall risk and betterment
After the 2020 fire, CDOT compared rockfall mitigation using risk and benefit-cost analysis. Subsequent debris flows exceeded some installed protection capacities.
Project evidence
Design & engineering
Partial recordThe FHWA case documents selected fence treatments, cost assumptions and the importance of distinguishing routine rockfall from larger debris-flow events.
Cost & estimating
Partial recordThe report lists a $2.692 million fence estimate and benefit-cost ratios for one- and five-year periods; other summary totals have different scopes.
Schedule & construction
Partial recordFences were installed in spring 2021; intense rainfall caused damaging debris flows in July 2021.
Completion & performance
Partial recordThe case records both reduced minor-rockfall disruption and damage during larger subsequent events.
Engineering methods
Suggested teaching exercise
Capstone project brief
Select a rockfall-protection strategy under changing post-fire hazard and explicitly describe the residual risk from events beyond its capacity.
Starting information & inputs
- Extract the source cost table, hazard categories and analysis periods.
- Verify energy units and fence specifications against design documents before using them; the summary’s unit labels require confirmation.
Suggested deliverables
- Recalculate the published benefit-cost comparison with transparent assumptions.
- Develop a fence layout concept, inspection triggers and a response to debris-flow exceedance.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.
Design questions
- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?