Cases / Project case study

Hywind Scotland — suction anchors for floating wind

Five floating turbines use mooring systems connected to seabed suction anchors. Project and decommissioning material support an integrated study of anchor capacity, installation, inspection and eventual removal.

Coastal and offshore foundationsLateral foundations and interactionSite investigationMonitoring and observational designEstimating, sequencing and project delivery
Hywind Scotland photographed from the sea on 22 June 2022. The turbine spars are visible above the water; the suction anchors and mooring arrangements are described in the linked project records.
Hywind Scotland photographed from the sea on 22 June 2022. The turbine spars are visible above the water; the suction anchors and mooring arrangements are described in the linked project records.Mike Pennington / Wikimedia Commons · Image source · CC BY-SA 2.0

Project evidence

Design & engineering

Partial record

Project sources describe the spar, mooring lines and suction anchors; the 2022 decommissioning programme gives asset-specific arrangements. Distinguish the floating turbine substructure from its seabed anchor foundation and do not transfer onshore monopile checks directly.

Sources: s1 · s2 · s3

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The operator records commissioning in 2017. The 2022 decommissioning document is a programme, not evidence that removal has occurred.

Sources: s1 · s2 · s3

Completion & performance

Partial record

The published field study reports subsea observations from 2018 and 2020. These observations show asset inspection opportunities and are not a complete geotechnical acceptance certificate.

Sources: s1 · s2 · s3

Engineering methods

Suction anchorsInclined cyclic loadingMooring–soil interactionInstallation and decommissioning

Suggested teaching exercise

Capstone project brief

Prepare a suction-anchor concept and inspection strategy for one mooring line, including cyclic demand and removal feasibility.

Starting information & inputs

  • Trace the three-point mooring arrangement and identify the anchor information actually supplied by the project.
  • Develop explicit study soil profiles and load envelopes when borehole/CPT data or proprietary design loads are unavailable.

Suggested deliverables

  • Compare installation suction, holding capacity and cyclic degradation scenarios, retaining the distinction between drained and undrained assumptions.
  • Prepare an ROV inspection plan, cable/mooring interaction review and a decommissioning sequence with geotechnical risks.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Why can an anchor meet a monotonic holding-capacity check yet remain unsuitable under repeated inclined mooring loads?
  • How would the preferred removal method change if the as-installed suction anchor has tilted or developed significant internal soil plugging?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records