I-15 reconstruction — soft-ground embankments and geofoam

Rapid highway reconstruction over soft lacustrine soils used geofoam, lime-cement columns, vertical drains, surcharge and staged MSE construction. UDOT reports ten-year performance.

Settlement and consolidationGround improvementReinforced soil and geosyntheticsMonitoring and observational designEstimating, sequencing and project delivery
The 100 South utility corridor during the Salt Lake City I-15 reconstruction, shown in the project authors’ Figure 2.
The 100 South utility corridor during the Salt Lake City I-15 reconstruction, shown in the project authors’ Figure 2.Steven Bartlett, Dawit Negussey, Mark Kimble and Michael Sheeley; published by Syracuse Geofoam Research Center · Image source · No open reuse license verified; original copyright retained

Project evidence

Design & engineering

Documented

The reports document alternative embankment systems and monitored geofoam sections, including the 100 South crossing.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The monitoring reports cover reconstruction and the following decade; extract dates for the chosen section rather than using a corridor-wide programme.

Sources: s1 · s2

Completion & performance

Partial record

Long-term settlement and numerical-model comparisons are available in the research reports.

Sources: s1 · s2

Engineering methods

EPS geofoamVertical drains and surchargeTwo-stage MSEConsolidation

Suggested teaching exercise

Capstone project brief

Choose an embankment solution above sensitive buried utilities and soft clay, then reconcile the design prediction with the long-term monitoring record.

Starting information & inputs

  • Extract stratigraphy, groundwater and construction loading from the selected instrumented section.
  • Digitize a clearly identified settlement series with units and dates.

Suggested deliverables

  • Compare earth fill, preload/drains and geofoam for settlement, time and buoyancy.
  • Prepare a staged-load calculation, utility protection detail and monitoring acceptance criteria.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.