Milltown Reservoir — dam removal and contaminated sediment remediation

Reservoir drawdown, dam removal and sediment excavation/capping were coordinated with river restoration and replacement of affected water-supply wells.

Contaminated ground and waste barriersDewatering and groundwaterEarthworks and pavement subgradesDams and leveesMonitoring and observational design
Remediation work at the Milltown Reservoir Superfund site in Montana.
Remediation work at the Milltown Reservoir Superfund site in Montana. The photograph shows excavation at the actual cleanup and dam-removal project.M Kustudia · Image source · CC BY-SA 3.0

Project evidence

Design & engineering

Partial record

EPA’s five-year review describes the implemented remedy and site components. Different operable units have different completion status.

Sources: s1 · s2

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The 2021 review records remedial work beginning in 2006 and final dam removal in March 2009; later site restoration and monitoring followed.

Sources: s1 · s2

Completion & performance

Partial record

The five-year review evaluates remedy performance; it does not state that every Clark Fork operable unit is complete.

Sources: s1 · s2

Engineering methods

Sediment dewateringExcavation and cappingGroundwater response

Suggested teaching exercise

Capstone project brief

Develop a phased contaminated-sediment removal plan while maintaining downstream water quality and protecting nearby wells.

Starting information & inputs

  • Extract the remedy scope for the reservoir operable unit, not the entire Clark Fork site.
  • Identify sediment handling, groundwater and restored-channel monitoring information.

Suggested deliverables

  • Prepare a dewatering/well-impact assessment and sediment handling sequence.
  • Compare excavation, onsite containment and capping with monitoring/closure criteria.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records

Excavation.jpg — image and reuse license ↗

Wikimedia Commons / M Kustudia · 2008

Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.

public-link · CC BY-SA 3.0 · Checked 2026-11-22