Cases / Project case study

Mosul Dam — maintenance grouting in soluble foundations

The dam overlies soluble limestone and gypsum. A rehabilitation programme strengthened maintenance grouting, equipment and instrumentation; continuing operation depends on sustained foundation management.

Dams and leveesSeepage and internal erosionRock slopes and foundationsMonitoring and observational designEstimating, sequencing and project delivery
Seepage east of and below the Mosul Dam spillway.
Seepage east of and below the Mosul Dam spillway. The source photograph documents the actual dam setting relevant to the foundation-management case.This image or file is a work of a U.S. Army Corps of Engineers soldier or employee, taken or made as part of that person's official duties. As a work of the U.S. federal government , the image is in the public domain . · Image source · Public domain

Project evidence

Design & engineering

Partial record

USACE’s project history explains the grouting-gallery purpose and the 2016–2019 rehabilitation. It does not portray dissolution as permanently eliminated.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The history documents the 2016–2019 task force; operation and maintenance remained the responsibility of Iraq’s Ministry of Water Resources.

Sources: s1

Completion & performance

Partial record

The source records equipment, workforce and instrumentation improvements, with continued grouting required.

Sources: s1

Engineering methods

Maintenance groutingKarst dissolutionInstrumented surveillance

Suggested teaching exercise

Capstone project brief

Develop an operations-linked grouting and surveillance plan for a dam on a dissolving foundation.

Starting information & inputs

  • Identify the soluble strata, access-gallery function and monitoring system described by the project team.
  • Define study groundwater chemistry and hydraulic gradients, marking them as assumptions where unpublished.

Suggested deliverables

  • Compare targeted and blanket grouting using permeability and grout-take scenarios.
  • Create inspection, drilling, instrumentation and response schedules that remain workable during outages.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Why is completion of a rehabilitation contract different from ending maintenance grouting?
  • How can changing grout take indicate either successful closure or a new flow path?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records

Mosul Dam seepage.jpg — image and reuse license ↗

Wikimedia Commons / This image or file is a work of a U.S. Army Corps of Engineers soldier or employee, taken or made as part of that person's official duties. As a work of the U.S. federal government , the image is in the public domain . · 2007

Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.

public-link · Public domain · Checked 2026-11-22