Cases / Project case study

US 64 Ocoee Gorge — emergency rockslide stabilization

Rockslides near Ocoee Dam 2 required rock removal, bolting and stabilization while weather and difficult access affected the reopening programme.

Rock slopes and foundationsSoil slopes and landslidesRetaining walls and anchorsEstimating, sequencing and project delivery
The Ocoee Gorge rockslide site on 20 November 2009, with the source author’s marked instability zones retained.
The Ocoee Gorge rockslide site on 20 November 2009, with the source author’s marked instability zones retained.Photograph published with Vanessa Bateman’s TDOT project article in ASHE SCANNER, Spring 2011 · Image source · No open reuse license verified; original copyright retained

Project evidence

Design & engineering

Partial record

The owner update documents stabilization quantities and sequencing. The technical conference account describes geological failure mechanisms.

Sources: s1 · s2

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The March 2010 owner update revised the expected reopening date to April 16 after weather delays; this was a forecast at publication.

Sources: s1 · s2

Completion & performance

Partial record

Progress quantities and a technical case paper are linked; a final account was not found.

Sources: s1 · s2

Engineering methods

Rock boltingScaling and controlled removalWeather-constrained work

Suggested teaching exercise

Capstone project brief

Develop a temporary and permanent rock-slope repair plan with worker exclusion zones and weather allowances.

Starting information & inputs

  • Extract the documented failures, access limitations and installed treatment quantities.
  • Identify discontinuity mapping and block geometry required for a study design.

Suggested deliverables

  • Prepare a kinematic stability assessment and concept bolt/fence layout.
  • Build a weather-sensitive schedule and quantity-based estimate.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records