Cases / Project case study

Olmsted Locks and Dam — marine construction and project controls

The navigation replacement became operational in 2018 after a long construction programme. USACE publishes project-control updates and completion material.

Dams and leveesPiles and drilled shaftsCoastal and offshore foundationsEstimating, sequencing and project delivery
Aerial view of the Olmsted Locks and Dam construction site, with lower pier shells being prepared for concrete placement.
Aerial view of the Olmsted Locks and Dam construction site, with lower pier shells being prepared for concrete placement. U.S. Army Corps of Engineers project photograph.LouisvilleUSACE · Image source · Public domain

Project evidence

Design & engineering

Partial record

The public project material supports marine construction and sequencing studies; detailed foundation design must be obtained from project-specific technical records.

Sources: s1 · s2

Cost & estimating

Partial record

The August 2018 scorecard distinguishes planned, earned and actual expenditure at its reporting date; it is not the final closeout account.

Sources: s1 · s2

Schedule & construction

Partial record

The 2018 update gives planned versus current completion/operational milestones; the ribbon-cutting release records the August 2018 event.

Sources: s1 · s2

Completion & performance

Partial record

Owner completion and award accounts are available; a full geotechnical completion report was not located.

Sources: s1 · s2

Engineering methods

Marine foundation constructionConstruction stagingEarned-value comparison

Suggested teaching exercise

Capstone project brief

Compare construction sequencing and foundation-installation risks for a major river structure while maintaining navigation.

Starting information & inputs

  • Extract the published work packages, dated cost scorecard and operational milestone.
  • Identify missing geotechnical design and production-rate information before pricing a study alternative.

Suggested deliverables

  • Develop a river-access, foundation-installation and closure sequence.
  • Reconcile planned, earned and actual cost terminology without treating budgeted quantities as final expenditures.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records