Cases / Project case study

One New Change — basement effects on St Paul’s groundwater

Redevelopment beside St Paul’s Cathedral required assessment of groundwater changes in shallow deposits supporting the historic structure. The designer describes conceptual and numerical groundwater modeling followed by construction monitoring.

Excavation supportDewatering and groundwaterShallow foundationsMonitoring and observational design
View from One New Change toward St Paul’s Cathedral.
View from One New Change toward St Paul’s Cathedral. The photograph shows the adjacent development and heritage structure whose groundwater interaction was assessed.Txllxt TxllxT · Image source · CC BY-SA 4.0

Project evidence

Design & engineering

Partial record

Arup explains the groundwater model and observed construction response. The public account does not provide the full calibrated model or authorize unrestricted basement work near the cathedral.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Not located in cited sources

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

Completion & performance

Partial record

The designer reports groundwater and structural monitoring during construction with negligible observed effect on the cathedral.

Sources: s1

Engineering methods

Groundwater modelingBasement cutoff effectsHeritage monitoring

Suggested teaching exercise

Capstone project brief

Assess whether a new basement diverts shallow groundwater enough to affect a neighboring heritage foundation.

Starting information & inputs

  • Extract the reported aquifer, foundation and basement relationships.
  • Identify man-made drainage and historic excavations that may change natural flow paths.

Suggested deliverables

  • Compare preconstruction and basement scenarios with recharge and permeability sensitivities.
  • Specify piezometers and structural surveys capable of distinguishing seasonal changes from construction effects.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Can a watertight basement cause damaging groundwater change without active dewatering?
  • Which calibration observations are needed before trusting a model’s small predicted effect?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.