Cases / Project case study

Texas SH 6 and SH 21 — expansive-subgrade distress

A TxDOT-funded project investigated swelling clay beneath distressed pavement sections and evaluated characterization and stabilization alternatives.

Expansive, collapsible and organic soilsLaboratory testing and parametersEarthworks and pavement subgradesSite investigation
The SH 6 study section in the original expansive-subgrade investigation, reproduced from the scanned Figure 6 photograph. The source scan has limited image quality.
The SH 6 study section in the original expansive-subgrade investigation, reproduced from the scanned Figure 6 photograph. The source scan has limited image quality.Seong-wan Park, Robert L. Lytton and Joe W. Button; Texas Transportation Institute / Texas A&M (1996) · Image source · No open reuse license verified; original copyright retained

Project evidence

Design & engineering

Partial record

The final research report covers site investigation, interpretation and treatment recommendations; the public catalog alone is not a rehabilitation plan set.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Not located in cited sources

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

Completion & performance

Partial record

A final research report is publicly indexed; complete construction records are not established.

Sources: s1

Engineering methods

Expansive subgradeMoisture/strength characterizationTreatment selection

Suggested teaching exercise

Capstone project brief

Develop a subgrade investigation and rehabilitation alternatives study for a selected documented pavement section.

Starting information & inputs

  • Extract one site’s profile, moisture and laboratory data from the final report.
  • Keep the two highway sections distinct when comparing properties and distress.

Suggested deliverables

  • Prepare a parameter register, moisture/heave mechanism assessment and test matrix.
  • Compare a moisture barrier, soil replacement and a verified stabilizer treatment.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records