Cases / Project case study

US 14 near Nicollet — preload and vertical drains

A highway embankment over organic clay used vertical drains, surcharge and staged filling, with remote monitoring of pore pressure and settlement.

Settlement and consolidationGround improvementExpansive, collapsible and organic soilsMonitoring and observational designEstimating, sequencing and project delivery
Vertical-drain construction on the US 14 embankment project near Nicollet, Minnesota.
Vertical-drain construction on the US 14 embankment project near Nicollet, Minnesota.Project photograph published by ASCE Geo-Institute; case submitted by Liang Chern Chow and Rich Lamb · Image source · No open reuse license verified; original copyright retained

Project evidence

Design & engineering

Partial record

The project authors describe drain spacing, surcharge, staged lifts, waiting periods and primary/post-surcharge secondary settlement.

Sources: s1

Cost & estimating

Partial record

The source lists estimated alternatives from $0.3 million for surcharge-only to $1.8 million for a land bridge; these are comparison estimates, not audited final costs.

Sources: s1

Schedule & construction

Partial record

The documented drain/surcharge design targeted a five-month waiting period after staged filling.

Sources: s1

Completion & performance

Partial record

The submitted case describes automated settlement, piezometric and earth-pressure monitoring.

Sources: s1

Engineering methods

Prefabricated vertical drainsStaged surchargeObservational consolidation

Published quantities & cost references

These values retain the scope and date basis of their cited source. Estimates, alternatives and partial packages are identified individually.

Source-backed project quantities and costs
ItemReported valueScope & source
Organic-soil thickness34 ftReported soft to very soft organic deposit above glacial till.Reported investigation interpretation.Source s1 · Project Summary/Scope
Typical drain spacing6 ftTriangular drain pattern over 80% of the embankment length.Reported design geometry.Source s1 · Project Summary/Scope
Surcharge-only estimate300,000 USDAlternative with extended waiting period.As reported; no escalation or inflation adjustment.Source s1 · Estimated Costs of Considered Options
Drains and surcharge estimate500,000 USDAlternative including extended wait and geotechnical monitoring.As reported; no escalation or inflation adjustment.Source s1 · Estimated Costs of Considered Options
Geofoam estimate800,000 USDLightweight-fill alternative.As reported; no escalation or inflation adjustment.Source s1 · Estimated Costs of Considered Options
Column-supported estimate1,200,000 USDColumn-supported embankment alternative.As reported; no escalation or inflation adjustment.Source s1 · Estimated Costs of Considered Options
Land-bridge estimate1,800,000 USDLand-bridge alternative.As reported; no escalation or inflation adjustment.Source s1 · Estimated Costs of Considered Options

Suggested teaching exercise

Capstone project brief

Design a preload programme that meets a highway opening deadline while controlling stability and residual settlement.

Starting information & inputs

  • Extract layer thicknesses, compression parameters and drain layout from the cited papers.
  • Use measured settlement and pore-pressure stages to define the observation period.

Suggested deliverables

  • Compare untreated waiting time with vertical/radial drainage and secondary compression.
  • Set stage-release criteria and a contingency for slow pore-pressure dissipation.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records

PVD and fill preloading — US Highway 14 ↗

ASCE Geo-Institute / named case-history author · 2024

Case submitted by the project manager and MnDOT foundations engineer; technical papers by Lamb/Chow/Bentler (2018, 2019).

public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22