Design & engineering
Partial recordThe project authors describe drain spacing, surcharge, staged lifts, waiting periods and primary/post-surcharge secondary settlement.
Sources: s1
Cost & estimating
Partial recordThe source lists estimated alternatives from $0.3 million for surcharge-only to $1.8 million for a land bridge; these are comparison estimates, not audited final costs.
Sources: s1
Schedule & construction
Partial recordThe documented drain/surcharge design targeted a five-month waiting period after staged filling.
Sources: s1
Completion & performance
Partial recordThe submitted case describes automated settlement, piezometric and earth-pressure monitoring.
Sources: s1