public-link · US federal agency case study; original credits retained · Checked 2026-11-22US 231, Lacey Springs — bridging a moving landslide
After a rainfall-triggered slide, ALDOT selected two bridges across the unstable area rather than reconstructing the road on the moving embankment.
Project evidence
Design & engineering
Partial recordFHWA documents alternative selection, drilled-shaft monitoring and construction delivery. It does not supply the full bridge/shaft design set.
Cost & estimating
Partial recordThe source reports $27.4 million for the repair/betterment and describes comparison with more expensive alternatives.
Schedule & construction
Partial recordThe bridges opened on 28 September 2020; the case describes incentives and advance purchase of casings and girders.
Completion & performance
Partial recordThe case discusses post-opening performance and ongoing instrumentation.
Engineering methods
Published quantities & cost references
These values retain the scope and date basis of their cited source. Estimates, alternatives and partial packages are identified individually.
| Item | Reported value | Scope & source |
|---|---|---|
| Repair/betterment cost | 27,400,000 USD | Two-bridge resilience solution; FHWA-reported package.As reported; no escalation or inflation adjustment.Source s1 · Project Snapshot and page 2 |
| Contract opening incentive | 2,490,000 USD | Incentive described for opening by 2 November 2020; not an extra cost assumed to have been paid.As reported; no escalation or inflation adjustment.Source s1 · Challenges and Lessons Learned |
Suggested teaching exercise
Capstone project brief
Compare slope stabilization with a bridge solution that transfers loads through unstable ground while preserving the road alignment.
Starting information & inputs
- Extract the evaluated alternatives, slope geometry constraints and monitored quantities.
- Identify the shear surface and pile-soil relative movement needed for a study shaft design.
Suggested deliverables
- Prepare an alternatives decision matrix and a lateral soil-loading sensitivity study.
- Develop an instrument layout with action levels and an accelerated procurement schedule.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.
Design questions
- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?