Cases / Project case study

US 231, Lacey Springs — bridging a moving landslide

After a rainfall-triggered slide, ALDOT selected two bridges across the unstable area rather than reconstructing the road on the moving embankment.

Soil slopes and landslidesPiles and drilled shaftsLateral foundations and interactionMonitoring and observational designEstimating, sequencing and project delivery
The completed US 231 bridges at Lacey Springs span the unstable slope, shown in the FHWA case study’s Figure 3.
The completed US 231 bridges at Lacey Springs span the unstable slope, shown in the FHWA case study’s Figure 3.Alabama Department of Transportation (ALDOT), published by FHWA · Image source · No open reuse license verified; original copyright retained

Project evidence

Design & engineering

Partial record

FHWA documents alternative selection, drilled-shaft monitoring and construction delivery. It does not supply the full bridge/shaft design set.

Sources: s1

Cost & estimating

Partial record

The source reports $27.4 million for the repair/betterment and describes comparison with more expensive alternatives.

Sources: s1

Schedule & construction

Partial record

The bridges opened on 28 September 2020; the case describes incentives and advance purchase of casings and girders.

Sources: s1

Completion & performance

Partial record

The case discusses post-opening performance and ongoing instrumentation.

Sources: s1

Engineering methods

Landslide avoidanceDrilled shaftsInstrumentation

Published quantities & cost references

These values retain the scope and date basis of their cited source. Estimates, alternatives and partial packages are identified individually.

Source-backed project quantities and costs
ItemReported valueScope & source
Repair/betterment cost27,400,000 USDTwo-bridge resilience solution; FHWA-reported package.As reported; no escalation or inflation adjustment.Source s1 · Project Snapshot and page 2
Contract opening incentive2,490,000 USDIncentive described for opening by 2 November 2020; not an extra cost assumed to have been paid.As reported; no escalation or inflation adjustment.Source s1 · Challenges and Lessons Learned

Suggested teaching exercise

Capstone project brief

Compare slope stabilization with a bridge solution that transfers loads through unstable ground while preserving the road alignment.

Starting information & inputs

  • Extract the evaluated alternatives, slope geometry constraints and monitored quantities.
  • Identify the shear surface and pile-soil relative movement needed for a study shaft design.

Suggested deliverables

  • Prepare an alternatives decision matrix and a lateral soil-loading sensitivity study.
  • Develop an instrument layout with action levels and an accelerated procurement schedule.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records