Cases / Project case study

Wolf Creek Dam — karst-foundation cutoff wall

A deep concrete barrier and associated grouting addressed seepage through the dam’s karst foundation. USACE documents completion and project scope.

Dams and leveesSeepage and internal erosionRock slopes and foundationsGround improvementEstimating, sequencing and project delivery
Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012.
Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012. U.S. Army Corps of Engineers photograph by Leon Roberts.Leon Roberts / U.S. Army Corps of Engineers · Image source · Public domain — U.S. federal government work

Project evidence

Design & engineering

Partial record

The completion account describes approximately 1,197 overlapping piles forming a 4,000-foot barrier. It does not provide a complete issued-for-construction package.

Sources: s1

Cost & estimating

Partial record

The March 2013 USACE account identifies a $594 million rehabilitation project; this is programme scope, not the wall’s final unit-price account.

Sources: s1

Schedule & construction

Partial record

Last pile placement was reported on 6 March 2013, nine months ahead of the then-planned December completion.

Sources: s1

Completion & performance

Partial record

USACE records barrier completion and the subsequent reservoir review.

Sources: s1

Engineering methods

Cutoff wallKarst groutingDam seepage control

Suggested teaching exercise

Capstone project brief

Compare a cutoff wall and grouting strategy for an operating dam over soluble rock, including continuity verification and reservoir constraints.

Starting information & inputs

  • Extract the documented barrier dimensions and geological problem.
  • Define an explicitly sourced or assumed permeability model for the study seepage calculation.

Suggested deliverables

  • Develop a seepage/uplift comparison and a wall-continuity QA plan.
  • Prepare a construction platform section and a reservoir/instrumentation hold-point sequence.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records