Cases / Project case study

Bluestone Dam — rock anchors and spillway-foundation protection

The safety programme combines anchoring, drainage and armor over the bedrock stilling basin. Construction must be staged while the spillway remains an active river-release route.

Dams and leveesRock slopes and foundationsScour and erosion protectionDewatering and groundwaterEstimating, sequencing and project delivery
Bluestone Dam in 2022, showing work in the spillway area.
Bluestone Dam in 2022, showing work in the spillway area. The photograph corresponds to the ongoing dam-safety programme.Antony-22 · Image source · CC BY-SA 4.0

Project evidence

Design & engineering

Partial record

USACE describes completed earlier phases and the ongoing stilling-basin work. The project is not labeled fully complete; the owner’s 2026 programme forecasts completion in 2030.

Sources: s1 · s2

Cost & estimating

Partial record

The 2020 notice identifies a $319.6 million Phase 5 contract. It is not a final cost for all phases.

Sources: s1 · s2

Schedule & construction

Partial record

The 2026 owner update reports one half complete and forecasts overall completion in 2030; this supersedes the older 2020 contract forecast.

Sources: s1 · s2

Completion & performance

Not located in cited sources

Complete as-built drawings and acceptance records were not found in the reviewed sources.

Engineering methods

Rock anchorsUplift drainageStilling-basin armorCofferdams

Suggested teaching exercise

Capstone project brief

Stage foundation anchoring and armor placement in half of an operating stilling basin.

Starting information & inputs

  • Extract the owner’s phase boundaries, diversion concept and uplift-control components.
  • Define a study flood window and rock discontinuity model for temporary and permanent checks.

Suggested deliverables

  • Check anchor demand and drain effectiveness for intact and blocked-drain scenarios.
  • Prepare a cofferdam sequence and flood-response plan with excavation hold points.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • How does temporary river diversion alter uplift beneath the work area?
  • Which inspection or proof-test result should delay concreting over an anchor zone?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records

Bluestone Dam 2022a.jpg — image and reuse license ↗

Wikimedia Commons / Antony-22 · 2022

Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.

public-link · CC BY-SA 4.0 · Checked 2026-11-22