Bolivar Dam — seepage barriers in outwash and fractured abutment rock

Rehabilitation combined a partial-depth barrier, blanket improvements, relief wells and an abutment grout curtain. The project authors explain construction problems in thin limestone units with open flow paths.

Dams and leveesSeepage and internal erosionRock slopes and foundationsMonitoring and observational design
Upstream view of Bolivar Dam in Ohio.
Upstream view of Bolivar Dam in Ohio. The actual embankment is shown; the later seepage barrier and grout curtain are largely below ground.Roseohioresident · Image source · Public domain

Project evidence

Design & engineering

Partial record

The USACE completion account identifies the combined risk-reduction measures. A technical paper details the abutment grouting and downstage treatment decisions.

Sources: s1 · s2

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The owner reports rehabilitation completion in October 2017.

Sources: s1 · s2

Completion & performance

Partial record

The completion account describes post-implementation evaluation and the resulting dam-safety classification.

Sources: s1 · s2

Engineering methods

Partial-depth cutoffRelief wellsAbutment groutingPiping control

Suggested teaching exercise

Capstone project brief

Compare seepage-control combinations for an embankment on permeable outwash beside fractured rock.

Starting information & inputs

  • Separate foundation flow, rock-contact erosion and gate-system issues in the owner record.
  • Extract the grout-curtain arrangement and treatment response to circulation losses.

Suggested deliverables

  • Draw a seepage model with wall, blanket and relief-well alternatives.
  • Specify drilling/grouting decisions and post-treatment piezometric performance criteria.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • How can a partial-depth barrier still reduce internal-erosion risk?
  • Where could seepage concentrate if the wall-to-rock transition is poorly treated?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records

Bolivar Dam (Ohio) upstream.jpg — image and reuse license ↗

Wikimedia Commons / Roseohioresident

Project image source. Unmodified publisher-generated display-size file; the original source URL and publisher metadata are retained. No AI-generated replacement or content alteration.

public-link · Public domain · Checked 2026-11-22