public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22Bowman Road Bridge — reinforced-soil abutments
The first production GRS integrated bridge system used reinforced-soil abutments. FHWA publishes a worked Bowman Road design and subsequent performance discussion.
Project evidence
Design & engineering
DocumentedThe archived FHWA worked example supplies bridge geometry, bearing loads, abutment sizing and internal/external checks. Use current guidance for a new design.
Cost & estimating
Partial recordFHWA reports $266,000 for the Bowman Road abutment, beams and waterproofing, compared with a $338,000 independent estimate for the conventional alternative. This historical comparison is not a certified final account.
Schedule & construction
Partial recordProduction construction occurred in 2005; the reviewed sources discuss accelerated construction rather than a complete contractor programme.
Completion & performance
Partial recordFHWA reports settlement and approach performance after opening.
Engineering methods
Published quantities & cost references
These values retain the scope and date basis of their cited source. Estimates, alternatives and partial packages are identified individually.
| Item | Reported value | Scope & source |
|---|---|---|
| GRS abutment cost | 95,000 USD | Bowman Road GRS-IBS abutment; historical comparison.As reported; no escalation or inflation adjustment.Source s2 · Table 1 |
| GRS beams and waterproofing | 171,000 USD | Bowman Road beams and waterproofing; historical comparison.As reported; no escalation or inflation adjustment.Source s2 · Table 1 |
| Reported GRS total | 266,000 USD | Combined abutment, beams and waterproofing in Table 1; not a certified final account.As reported; no escalation or inflation adjustment.Source s2 · Table 1 |
| Conventional alternative estimate | 338,000 USD | Independent cost estimate for the alternative in Table 1; not an awarded contract.As reported; no escalation or inflation adjustment.Source s2 · Table 1 |
Suggested teaching exercise
Capstone project brief
Develop a replacement rural bridge abutment using the Bowman Road example as the reference project; compare reinforced soil with a conventional abutment.
Starting information & inputs
- Extract span, reactions, abutment dimensions and reinforcement assumptions from the worked example.
- Identify scour, drainage and foundation information that the example assumes.
Suggested deliverables
- Reproduce the reference checks and document any difference caused by a current design basis.
- Prepare an abutment section, reinforcement schedule, drainage detail and bridge-approach settlement check.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.
Design questions
- Which site data control the decision, and what additional investigation would reduce uncertainty?
- How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?
Sources & original records
FHWA · 2019
public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22FHWA · 2011
public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22FHWA · 2012
public-link · US federal publication; preserve original credits · Checked 2026-11-22FHWA · 2011
public-link · US federal publication; preserve original credits · Checked 2026-11-22FHWA · 2019
public-link · US federal publication; preserve original credits · Checked 2026-11-22