Cases / Project case study

Center Hill Dam — grouting, cutoff wall and stabilizing berm

A staged rehabilitation treated foundation seepage and auxiliary-dam risks using grouting, a deep cutoff wall and a roller-compacted-concrete berm.

Dams and leveesSeepage and internal erosionRock slopes and foundationsGround improvementEstimating, sequencing and project delivery
The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020..
The roller-compacted-concrete berm at the Center Hill auxiliary dam, shown in the USACE project-completion image collection published in July 2020.Leon Roberts / U.S. Army Corps of Engineers · Image source · Public domain — U.S. federal government work

Project evidence

Design & engineering

Partial record

USACE describes three major repair phases and their completed components; detailed construction plans are not attached to the completion release.

Sources: s1

Cost & estimating

Partial record

The completion release reports $353 million overall, with $107 million grouting, $122 million cutoff and $50 million berm contracts; scopes differ from the programme total.

Sources: s1

Schedule & construction

Partial record

Reported phases were grouting in 2008–2010, cutoff in 2012–2015 and final berm completion celebrated in July 2020.

Sources: s1

Completion & performance

Partial record

The USACE release documents the final repair phase and constructed features.

Sources: s1

Engineering methods

Foundation groutingCutoff wallStabilizing berm

Suggested teaching exercise

Capstone project brief

Develop a risk-based sequence of dam repairs in which initial grouting also informs the later cutoff design.

Starting information & inputs

  • Extract phase scope, wall depth and published contract-period information.
  • Identify the piezometric and geological evidence needed to assess each repaired failure mode.

Suggested deliverables

  • Prepare a seepage/stability failure-mode map and an investigation-to-construction decision process.
  • Compare a single-stage programme with the documented phased strategy.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records