Cases / Project case study

Clearwater Dam — karst pretreatment and a hanging cutoff

A sinkhole prompted foundation exploration and grouting before construction of a deep seepage cutoff. The owner explains why treating solution-enlarged fractures was necessary for slurry-supported excavation.

Dams and leveesSeepage and internal erosionRock slopes and foundationsGround improvement
Aerial view of construction equipment along the crest of Clearwater Lake Dam in Missouri.
Aerial view of Clearwater Lake Dam in Missouri during the rehabilitation works, from Keller’s project account. The photograph shows construction along the dam crest.Keller / Keller Management Services, LLC · Image source · No open reuse license verified; original copyright retained

Project evidence

Design & engineering

Partial record

USACE’s rehabilitation account describes the grouting sequence, epikarst treatment and cutoff construction. Its forecast of later completion is retained as a forecast rather than a final-account statement.

Sources: s1 · s2

Cost & estimating

Partial record

The owner page forecast approximately $240 million for the overall rehabilitation. It is not presented here as a verified final account.

Sources: s1 · s2

Schedule & construction

Partial record

USACE records placement of the final cutoff panel on 6 December 2011; the page’s remaining-work milestones were forecasts.

Sources: s1 · s2

Completion & performance

Not located in cited sources

Complete as-built drawings and acceptance records were not found in the reviewed sources.

Engineering methods

Karst groutingHydromill cutoffSlurry loss control

Suggested teaching exercise

Capstone project brief

Design a pretreatment and cutoff-wall sequence for a dam with connected karst features.

Starting information & inputs

  • Extract the reported seepage problem and the relationship between pretreatment and panel excavation.
  • Define a study range for rock permeability and connected-void sizes.

Suggested deliverables

  • Compare seepage paths around a hanging cutoff and through a locally defective panel.
  • Specify staged grouting, slurry-loss response and test-panel acceptance requirements.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Why can grouting be necessary even when a cutoff wall is the main permanent barrier?
  • How should treatment change when drilling loses circulation in a solution feature?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records