Cases / Project case study

East Branch Dam — cutoff-wall construction and verification

A dam-repair programme installed a cutoff wall to reduce foundation seepage. USACE reports the contract and return toward normal operations; the technical literature discusses wall verification drilling.

Dams and leveesSeepage and internal erosionGround improvementMonitoring and observational design
East Branch Clarion River Lake and Dam near Wilcox, Pennsylvania.
East Branch Clarion River Lake and Dam near Wilcox, Pennsylvania. USACE photograph of the dam treated by the later seepage-cutoff rehabilitation.Margaret Luzier, U.S. Army Corps of Engineers · Image source · Public domain

Project evidence

Design & engineering

Partial record

Owner releases establish the rehabilitation scope and outcome. The cited verification reference is an abstract, so complete verification datasets are not claimed locally.

Sources: s1 · s2 · s3

Cost & estimating

Partial record

The owner reports a $132.5 million cutoff-wall rehabilitation contract awarded in 2014, not a certified final expenditure.

Sources: s1 · s2 · s3

Schedule & construction

Not located in cited sources

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

Completion & performance

Partial record

The owner’s 2020 releases describe repair completion and reservoir-operating changes.

Sources: s1 · s2 · s3

Engineering methods

Seepage cutoffWall continuityVerification drilling

Suggested teaching exercise

Capstone project brief

Plan a cutoff-wall quality-assurance programme that can demonstrate continuity without damaging the finished barrier.

Starting information & inputs

  • Extract the owner’s treatment objective and the technical abstract’s verification problem.
  • Specify study foundation permeability zones and their uncertainty before comparing barrier options.

Suggested deliverables

  • Estimate seepage reduction for intact and defective wall scenarios.
  • Develop test-panel, drilling, permeability-testing and reservoir-response acceptance criteria.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Can a low-permeability test core establish continuity between adjacent panels?
  • What monitoring evidence is needed before relaxing an operating restriction?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.