Cases / Project case study

Folsom auxiliary spillway — rock excavation and foundation preparation

The auxiliary spillway required major rock excavation and preparation of the control-structure foundation before concrete placement.

Rock slopes and foundationsDams and leveesExcavation supportEstimating, sequencing and project delivery
Rock excavation for the Folsom Dam auxiliary spillway, April 2012.
Rock excavation for the Folsom Dam auxiliary spillway, April 2012. U.S. Army Corps of Engineers construction photograph.U.S. Army Corps of Engineers Sacramento District · Image source · Public domain

Project evidence

Design & engineering

Partial record

USACE construction accounts describe blasting completion, foundation cleaning and the subsequent control structure and chute.

Sources: s1 · s2

Cost & estimating

Partial record

USACE describes a $900 million cooperative effort, a programme total rather than a rock-excavation unit-rate schedule.

Sources: s2

Schedule & construction

Partial record

The source records initial excavation in 2008, final concrete stages in 2016 and the October 2017 completion ceremony.

Sources: s2

Completion & performance

Partial record

The owner’s completion release identifies the constructed auxiliary spillway.

Sources: s2

Engineering methods

Rock excavationFoundation preparationControlled blasting

Suggested teaching exercise

Capstone project brief

Plan a rock-foundation excavation and acceptance programme beside an operating dam and public transport route.

Starting information & inputs

  • Extract published construction stages and final structure dimensions.
  • Establish study discontinuity, groundwater and blast-vibration parameters explicitly.

Suggested deliverables

  • Prepare a temporary rock-slope/bench concept and foundation mapping checklist.
  • Design sequencing between blasting, cleaning, drainage, acceptance and concrete placement.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records