Cases / Project case study

Founders/Meadows Bridge — footings on reinforced soil

The bridge and approach roadway were supported on geosynthetic-reinforced segmental walls. A material-testing and instrumentation programme followed the experimental arrangement.

Reinforced soil and geosyntheticsShallow foundationsLaboratory testing and parametersMonitoring and observational design
The completed Founders/Meadows Bridge and its reinforced-soil approaches, viewed from the southwest. Original project photograph in Report 1, Figure B-3.
The completed Founders/Meadows Bridge and its reinforced-soil approaches, viewed from the southwest. Original project photograph in Report 1, Figure B-3.CDOT research team: Naser Abu-Hejleh, William (Skip) Outcalt, Trever Wang and Jorge G. Zornberg (2000) · Image source · No open reuse license verified; original copyright retained

Project evidence

Design & engineering

Documented

CDOT Report 1 covers design, materials, construction and instruments; Report 2 evaluates wall performance.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

CDOT reports completion in July 1999.

Sources: s1 · s2

Completion & performance

Partial record

The two reports contain construction observations and instrumented performance results.

Sources: s1 · s2

Engineering methods

Footings on MSEGeosynthetic reinforcementMeasured deformation

Suggested teaching exercise

Capstone project brief

Evaluate the load path from bridge footing through reinforced soil and compare calculated wall movements with the reported observations.

Starting information & inputs

  • Extract the front-wall geometry, footing loads and reinforcement properties.
  • Tabulate measured displacement/stress locations and distinguish construction stages.

Suggested deliverables

  • Develop bearing, sliding, internal stability and deformation checks for the reference section.
  • Prepare an instrumentation layout and explain which measurements can test each design assumption.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records