public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22Osman Gazi Bridge — seismic caissons on gravel beds
The suspension bridge combines offshore caisson foundations with improved ground and a gravel interface intended to accommodate extreme seismic movement. Published accounts describe soil–structure interaction and marine installation.
Project evidence
Design & engineering
Partial recordThe design paper models gravel-bed and reinforced-subsoil response using nonlinear foundation elements. Contractor records explain floating and sinking the caissons onto prepared crushed rock. A controlled-sliding concept needs both displacement and residual-performance checks.
Cost & estimating
Not located in cited sourcesA project-specific estimate, bid schedule or final account was not found in the reviewed sources.
Schedule & construction
Partial recordIHI describes a 42-month construction period. Treat that as the contractor’s overall project account, not a detailed foundation activity schedule.
Completion & performance
Partial recordThe construction accounts document the built crossing; the design-stage soil–structure model is not a substitute for measured earthquake performance.
Engineering methods
Suggested teaching exercise
Capstone project brief
Compare fixed-base and nonlinear-foundation representations for a bridge tower supported on a prepared gravel interface.
Starting information & inputs
- Extract foundation arrangement, soil improvement and the interface behaviour from the design-stage paper.
- Identify the earthquake performance objectives and distinguish assumptions in the analysis from measured field response.
Suggested deliverables
- Construct a reduced nonlinear spring/interface model and compare sliding, rocking and residual displacement under selected study motions.
- Prepare seabed preparation, caisson placement, survey-tolerance and post-earthquake inspection requirements.
- A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
- A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.
Design questions
- When can intentional foundation sliding reduce structural demand while increasing permanent displacement and service-restoration work?
- Which installation tolerances and seabed observations are needed to make the assumed gravel-interface behaviour credible?
Sources & original records
IHI Infra-square
public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22Webuild
public-link · Publisher-hosted; redistribution permission not established · Checked 2026-11-22Erdmkiliic · 2016
Project image source. Provider-generated width-limited JPEG preview; no local crop, retouching, added text or recolouring.
public-link · CC BY-SA 4.0 · Checked 2026-11-22