Cases / Project case study

Palm Jumeirah — densification of reclaimed sand

The artificial island’s reclaimed sand was treated by vibrocompaction before infrastructure construction. The project’s visitor centre explains the working sequence and its role in controlling settlement and liquefaction susceptibility.

Ground improvementCoastal and offshore foundationsEarthquakes and liquefactionEarthworks and pavement subgrades
Palm Jumeirah viewed from a helicopter in May 2008.
Palm Jumeirah viewed from a helicopter in May 2008. The actual reclaimed island is shown after the principal ground-treatment period.Imre Solt · Image source · CC BY-SA 3.0

Project evidence

Design & engineering

Partial record

The owner-associated account describes the compaction process and construction sequence. Site-specific CPT data and the complete foundation design package are not provided.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Not located in cited sources

A dated project programme was not found in the reviewed sources; develop a study schedule from the documented method.

Completion & performance

Not located in cited sources

Complete as-built drawings and acceptance records were not found in the reviewed sources.

Engineering methods

VibrocompactionDensification verificationLiquefaction screening

Suggested teaching exercise

Capstone project brief

Plan a field trial and acceptance programme for vibrocompaction of a reclaimed waterfront building plot.

Starting information & inputs

  • Use the source to define the treatment sequence and imported/backfill material interfaces.
  • Specify a study sand profile and groundwater level, then identify tests required before adopting design parameters.

Suggested deliverables

  • Compare trial-grid spacings using settlement and CPT-based acceptance criteria.
  • Develop treatment quantities, verification coverage and a response to refusal or poor improvement.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Why should vibratory power records be supplemented with independent ground testing?
  • How do fines content and drainage affect the suitability of vibrocompaction?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.