Cases / Project case study

Seattle SR 99 tunnel — soft-ground tunnelling and settlement

The bored-tunnel replacement passed beneath downtown Seattle. Owner material includes geology/soils assessment, procurement information and completion history.

Tunnels and underground worksExcavation supportDewatering and groundwaterMonitoring and observational designEstimating, sequencing and project delivery
The SR 99 tunnel project’s Bertha retrieval and repair site in Seattle, July 2015.
The SR 99 tunnel project’s Bertha retrieval and repair site in Seattle, July 2015. The photograph shows the actual construction setting after the machine’s front section had been lifted for repairs.SounderBruce from Seattle, United States · Image source · CC BY-SA 2.0

Project evidence

Design & engineering

Partial record

The environmental geology/soils appendix and design-build procurement records establish ground risks and contract context, not a complete as-built tunnel design.

Sources: s1 · s2 · s3

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

WSDOT identifies February 2019 completion; procurement and construction milestones are available on the owner pages.

Sources: s1 · s2 · s3

Completion & performance

Partial record

The owner’s completed-project page records the outcome and links supporting material.

Sources: s1 · s2 · s3

Engineering methods

Earth-pressure-balance tunnellingSettlementGroundwater control

Suggested teaching exercise

Capstone project brief

Develop a settlement-risk and monitoring plan for an urban bored tunnel, including shaft construction and dewatering interactions.

Starting information & inputs

  • Extract route geology, groundwater and protected assets from Appendix P.
  • Separate environmental alternatives from the subsequently selected design-build solution.

Suggested deliverables

  • Estimate surface settlement for documented or explicitly assumed loss scenarios.
  • Prepare shaft/uplift checks and a response plan for unexpected settlement.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records

Bertha TBM retrieval site.jpg — image and reuse license ↗

Wikimedia Commons / SounderBruce from Seattle, United States · 2015

Project image source. Unmodified image bytes from the publisher’s selected-size file; only responsive display sizing is applied by the website.

public-link · CC BY-SA 2.0 · Checked 2026-11-22