Cases / Project case study

Teton Dam — internal erosion and first-filling investigation

The first-filling failure is documented through the Bureau of Reclamation’s history and the independent investigation report.

Dams and leveesSeepage and internal erosionRock slopes and foundationsSite investigation
The breach of Teton Dam, June 5, 1976.
The breach of Teton Dam, June 5, 1976. Historical project photograph from the U.S. Bureau of Reclamation collection.U.S. Bureau of Reclamation / U.S. National Archives at Denver · Image source · Public domain

Project evidence

Design & engineering

Partial record

The official archive provides the original design/foundation investigation context and the 1976 failure report; the dam was not rebuilt.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

Failure occurred on 5 June 1976; the independent panel report was submitted in December 1976.

Sources: s1

Completion & performance

Partial record

The official archive links the investigation and contemporary photographs; there is no completed replacement-dam record.

Sources: s1

Engineering methods

Internal erosionFilters and contactsFirst-filling surveillance

Suggested teaching exercise

Capstone project brief

Evaluate alternative core/filter and foundation-treatment concepts using the investigation as a forensic reference, without treating a classroom redesign as an approved remedy.

Starting information & inputs

  • Extract foundation geology, core/filter arrangement and reservoir-filling observations.
  • Separate contemporary records from later interpretations of the failure mechanism.

Suggested deliverables

  • Prepare a potential-failure-mode analysis and a filtered-contact concept.
  • Design a first-filling monitoring and escalation plan.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.

Sources & original records