Cases / Project case study

West Davis Highway ramp — lightweight fill beside live transport

UDOT used geofoam blocks for the ramp connecting West Davis Highway to southbound I-15, with existing transport infrastructure constraining allowable settlement.

Ground improvementSettlement and consolidationEarthworks and pavement subgradesEstimating, sequencing and project delivery
Aerial view of the West Davis Highway geofoam ramp under construction beside live transport routes.
Aerial view of geofoam ramp construction on the West Davis Highway connection to southbound I-15, Farmington, Utah. UDOT published this project photograph in August 2023.Utah Department of Transportation (UDOT) · Image source · UDOT public reuse with attribution — social-media policy

Project evidence

Design & engineering

Partial record

The owner describes the lightweight-fill choice and construction; detailed geotechnical design calculations are not supplied on the news page.

Sources: s1

Cost & estimating

Not located in cited sources

A project-specific estimate, bid schedule or final account was not found in the reviewed sources.

Schedule & construction

Partial record

The owner update documents ramp construction in August 2023.

Sources: s1

Completion & performance

Partial record

The source includes construction photographs; complete as-built drawings were not established.

Sources: s1

Engineering methods

EPS geofoamSettlement controlConstruction access

Suggested teaching exercise

Capstone project brief

Develop a lightweight ramp concept while preserving adjacent road and rail service.

Starting information & inputs

  • Use the owner’s site description and identify missing foundation-soil data.
  • Set an explicit study profile, load case and allowable movement with instructor approval.

Suggested deliverables

  • Check foundation stress, settlement, block compression and groundwater uplift.
  • Draw block arrangement, pavement separation and lateral protection details.
  • A quantity takeoff and priced estimate with dated rate sources; separate historical project costs from the study estimate.
  • A construction sequence, programme and risk register tied to investigation, access, monitoring and hold points.

Design questions

  • Which site data control the decision, and what additional investigation would reduce uncertainty?
  • How would the proposed solution change under the stated sensitivity cases, construction constraints and performance limits?

The brief is a proposed educational exercise based on the cited project, not the original designer's instruction or a complete construction document set.