Foundation Design · Cases

Find Engineering Cases

Documented projects, design decisions and lessons for engineering practice and capstone studies.

Owner, location & access
Clear filters

35 of 117 project case studies

Aerial view of construction equipment along the crest of Clearwater Lake Dam in Missouri.

US Army Corps of Engineers · 2011

Clearwater Dam — karst pretreatment and a hanging cutoff

A sinkhole prompted foundation exploration and grouting before construction of a deep seepage cutoff. The owner explains why treating solution-enlarged fractures was necessary for slurry-supported excavation.

Dams and leveesSeepage and internal erosionRock slopes and foundations
Interior of the Marmaray tunnel project in 2012.

Republic of Türkiye transport authorities · 2013

Marmaray crossing — immersed-tunnel foundations in seismic ground

The immersed crossing combined a gravel foundation, under-base grouting and treatment of liquefiable deposits. A project paper explains element connections and the transition to adjacent bored tunnels under severe seismic demands.

Tunnels and underground worksEarthquakes and liquefactionGround improvement
Construction of the future 86th Street station in November 2013.

Metropolitan Transportation Authority · 2017

Second Avenue Subway Phase 1 — ground freezing at a TBM launch

Unexpected poor ground near the east running-tunnel launch required a revised sequence. The construction manager describes soil freezing while the TBM first advanced through the western alignment.

Tunnels and underground worksGround improvementMonitoring and observational design
Excavation beneath Northern Boulevard in Queens in December 2012.

Metropolitan Transportation Authority · 2013

East Side Access — frozen support beneath Northern Boulevard

A short mined connection beneath active transport infrastructure used a frozen soil arch for temporary support and groundwater cutoff. The project sources distinguish local freezing from the wider East Side Access tunnel programme.

Tunnels and underground worksGround improvementDewatering and groundwater
The northbound entrance to Kuala Lumpur’s SMART Tunnel.

Department of Irrigation and Drainage / Malaysian Highway Authority · 2007

SMART Tunnel — tunnelling through urban karst

The combined stormwater and road tunnel passes through highly irregular limestone and overlying deposits. The builder and ground-treatment contractor describe slurry-shield excavation, grouting and sinkhole-management challenges.

Tunnels and underground worksRock slopes and foundationsDewatering and groundwater
Liquefaction damage in Minatojima-Nakamachi on Kobe’s Port Island on 17 January 1995.

Port of Kobe / Japanese port researchers · 1995

Kobe Port — quay-wall displacement during liquefaction

Many caisson quay walls moved seaward during the 1995 earthquake. Port researchers studied the combined contributions of inertia and excess pore pressure beneath and behind the walls.

Earthquakes and liquefactionRetaining walls and anchorsCoastal and offshore foundations
The entrance to the Svalbard Global Seed Vault in February 2020, after the 2016–2019 upgrade period. The photograph shows the actual facility; buried tunnel details are documented by the linked owner sources.

Norwegian Ministry of Agriculture and Food / Statsbygg · 2019

Svalbard Seed Vault — tunnel waterproofing and frozen ground

The Seed Vault upgrade replaced its access tunnel with a watertight concrete structure and moved heat-producing services. The construction account includes artificial ground freezing to support the replacement works.

Permafrost and cold regionsTunnels and underground worksGround improvement
The Osman Gazi Bridge across Izmit Bay. The buried and submerged foundation details are documented in the linked design and construction sources.

Gebze–Orhangazi–Izmir motorway project · 2016

Osman Gazi Bridge — seismic caissons on gravel beds

The suspension bridge combines offshore caisson foundations with improved ground and a gravel interface intended to accommodate extreme seismic movement. Published accounts describe soil–structure interaction and marine installation.

Lateral foundations and interactionEarthquakes and liquefactionGround improvement
The Eastern Scheldt storm-surge barrier viewed from Westerschouwen in January 2025. Its submerged foundation mats and scour-protection layers are explained in the engineering sources, rather than inferred from this surface view.

Rijkswaterstaat · 1986

Eastern Scheldt Barrier — foundation mats and scour resilience

The movable barrier retains tidal exchange while closing during severe water levels. Its foundation and bed-protection concepts provide a case on erosion resistance, interface stability and long-term renewal of marine structures.

Coastal and offshore foundationsShallow foundationsScour and erosion protection
Construction of the MOSE project at the Lido inlet, Venice, in mid-2009. This is a construction-stage photograph; the later operational barrier and monitoring results are described separately.

Italian Ministry of Infrastructure / MOSE project · 2025

Venice MOSE — marine caisson placement and movement monitoring

The movable lagoon barriers rely on accurately positioned marine caissons and controlled differential movement. Designer accounts and published deformation surveys connect foundation construction with operational alignment requirements.

Coastal and offshore foundationsShallow foundationsSettlement and consolidation

From project evidence to a design study

Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.

Topic coverage

Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.