Bowman Road Bridge — reinforced-soil abutments
The first production GRS integrated bridge system used reinforced-soil abutments. FHWA publishes a worked Bowman Road design and subsequent performance discussion.
Foundation Design · Cases
Documented projects, design decisions and lessons for engineering practice and capstone studies.
18 of 117 project case studies
The first production GRS integrated bridge system used reinforced-soil abutments. FHWA publishes a worked Bowman Road design and subsequent performance discussion.
The bridge and approach roadway were supported on geosynthetic-reinforced segmental walls. A material-testing and instrumentation programme followed the experimental arrangement.
A distribution-centre site on former strip-mine ground combined dynamic compaction with aggregate piers where wet, weak areas did not respond adequately.
The submitted case describes dynamic compaction of variable former landfill material before shallow foundations and slabs were constructed.
A hangar expansion used dynamic compaction to reduce liquefaction susceptibility in sandy fill and outwash, with vibration controls beside operating airport facilities.
The arena foundation study compared deep foundations with spread footings on improved ground. Test sections supported the selected compaction and replacement approach.
The 2012 trials compared shallow rafts, mixing columns, a perimeter curtain and densification approaches to support residential foundation repair and rebuilding.
The NTSB investigation documents the bridge collapse after scour undermined spread-footing support, including construction, protection and inspection issues.
A heritage foundation was stabilized by carefully removing soil beneath its north side. Published post-intervention observations connect rotation, settlement and groundwater control.
The tower uses a piled raft in weak sedimentary rock. The foundation designer publishes an analysis process linking ground characterization, trial pile testing and settlement predictions for super-tall towers.
The bridge foundations combine large caissons, a gravel interface and steel inclusions in weak seabed deposits. The designer distinguishes this system from piles structurally connected to a raft.
The original airport terminal crosses former island rock and newly reclaimed ground. The designer describes a range of foundation types adapted to these contrasting conditions; a contemporaneous paper documents vibrocompaction of marine sand fill.
Published investigations compare sites that did and did not liquefy, linking penetration tests, recovered sand samples and cyclic strength. Building tilting demonstrates the importance of ground response even when the superstructure remains comparatively intact.
Redevelopment beside St Paul’s Cathedral required assessment of groundwater changes in shallow deposits supporting the historic structure. The designer describes conceptual and numerical groundwater modeling followed by construction monitoring.
The Antarctic station sits on ski-supported hydraulic legs that allow annual raising and relocation. This is a foundation-maintenance and construction-logistics case on moving, accumulating snow and ice.
The elevated station experiences nonuniform support-column settlement in deep permanent snow. USACE reports analyze surveys, floor levelness and maintenance decisions, making a useful observational-design case.
The movable barrier retains tidal exchange while closing during severe water levels. Its foundation and bed-protection concepts provide a case on erosion resistance, interface stability and long-term renewal of marine structures.
The movable lagoon barriers rely on accurately positioned marine caissons and controlled differential movement. Designer accounts and published deformation surveys connect foundation construction with operational alignment requirements.
| Title | Type | Owner / location | Year | Access |
|---|---|---|---|---|
| Bowman Road Bridge — reinforced-soil abutments | Design and construction | Defiance CountyDefiance County, Ohio | 2005 | Original documents |
| Founders/Meadows Bridge — footings on reinforced soil | Design and construction | Colorado Department of TransportationCastle Rock, Colorado | 1999 | Study materials |
| Olyphant distribution centre — variable mine-spoil improvement | Design and construction | D&L RealtyOlyphant, Pennsylvania | 2022 | Study materials |
| Tempe Marketplace — foundations over former landfill | Redevelopment | Owner not stated in reviewed caseTempe, Arizona | 2015 | Study materials |
| JFK hangar expansion — liquefaction mitigation by compaction | Design and construction | Airport project owner not stated in reviewed caseQueens, New York | 1999 | Study materials |
| Prudential Center — shallow foundations after improvement | Redevelopment | New Jersey DevilsNewark, New Jersey | 2006 | Study materials |
| Canterbury residential ground-improvement trials | Field demonstration | New Zealand building ministry and trial partnersChristchurch, Canterbury | 2012 | Study materials |
| Schoharie Creek Bridge — scour and foundation inspection | Forensic investigation | New York State Thruway AuthorityNear Amsterdam, New York | 1987 | Original documents |
| Leaning Tower of Pisa — controlled underexcavation | Design, construction and performance | Italian Government / Opera della Primaziale PisanaPisa | 2008 | Study materials |
| Burj Khalifa — piled-raft settlement design | Design, construction and performance | Emaar PropertiesDubai | 2010 | Study materials |
| Rion–Antirion Bridge — seismic caissons on improved seabed | Design, construction and performance | GefyraGulf of Corinth | 2004 | Study materials |
| Hong Kong International Airport — foundations across rock and reclamation | Design, construction and performance | Airport Authority Hong KongChek Lap Kok | 1998 | Study materials |
| Niigata earthquake — contrasting liquefied and non-liquefied sites | Design, construction and performance | Japanese earthquake investigatorsNiigata | 1964 | Study materials |
| One New Change — basement effects on St Paul’s groundwater | Design, construction and performance | Land SecuritiesCity of London | 2010 | Study materials |
| Halley VI — relocatable foundations on accumulating snow | Design, construction and performance | British Antarctic SurveyBrunt Ice Shelf, Antarctica | 2017 | Study materials |
| South Pole Station — snow-foundation settlement and levelling | Design, construction and performance | National Science Foundation / U.S. Antarctic ProgramGeographic South Pole | 2019 | Study materials |
| Eastern Scheldt Barrier — foundation mats and scour resilience | Design, construction and performance | RijkswaterstaatZeeland | 1986 | Study materials |
| Venice MOSE — marine caisson placement and movement monitoring | Design, construction and performance | Italian Ministry of Infrastructure / MOSE projectVenice Lagoon | 2025 | Original documents |
Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.
Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.