Bowman Road Bridge — reinforced-soil abutments
The first production GRS integrated bridge system used reinforced-soil abutments. FHWA publishes a worked Bowman Road design and subsequent performance discussion.
Foundation Design · Cases
Documented projects, design decisions and lessons for engineering practice and capstone studies.
8 of 117 project case studies
The first production GRS integrated bridge system used reinforced-soil abutments. FHWA publishes a worked Bowman Road design and subsequent performance discussion.
The bridge and approach roadway were supported on geosynthetic-reinforced segmental walls. A material-testing and instrumentation programme followed the experimental arrangement.
Rapid highway reconstruction over soft lacustrine soils used geofoam, lime-cement columns, vertical drains, surcharge and staged MSE construction. UDOT reports ten-year performance.
Following Hurricane Michael, roadway reconstruction incorporated articulated concrete blocks over filter fabric and bedding to reduce recurring embankment erosion.
After the 2019 flood damaged the road embankment, Iowa DOT selected anchored concrete-block matting and evaluated recurring-damage economics.
Former waste mounds are being converted to parkland above engineered cover and gas/leachate systems. The project explains how cover layers limit infiltration, protect barriers and drain slopes.
Constrained highway construction used retaining structures in a river canyon. The reinforced-wall studies examine movement over compressible deposits and the importance of separating reinforced-fill performance from foundation settlement.
The reinforced slope supporting a runway extension failed in 2015. Published investigations examine the fill–rock interface, material strength selection and global failure mechanisms, offering a strong forensic capstone.
| Title | Type | Owner / location | Year | Access |
|---|---|---|---|---|
| Bowman Road Bridge — reinforced-soil abutments | Design and construction | Defiance CountyDefiance County, Ohio | 2005 | Original documents |
| Founders/Meadows Bridge — footings on reinforced soil | Design and construction | Colorado Department of TransportationCastle Rock, Colorado | 1999 | Study materials |
| I-15 reconstruction — soft-ground embankments and geofoam | Design and construction | Utah Department of TransportationSalt Lake City, Utah | 2001 | Study materials |
| US 98, Florida — coastal roadway revetment | Rehabilitation | Florida Department of TransportationFlorida Panhandle | 2018 | Original documents |
| US 34, Iowa — flood-resistant embankment matting | Rehabilitation | Iowa Department of TransportationMills County, Iowa | 2021 | Original documents |
| Freshkills Park — landfill cap, drainage and long-term integrity | Design, construction and performance | New York CityStaten Island, New York | 2011 | Study materials |
| Glenwood Canyon — reinforced walls on compressible foundations | Design, construction and performance | Colorado Department of TransportationI-70, Colorado | 1992 | Study materials |
| Yeager Airport — reinforced-slope failure and degraded rock | Failure investigation and lessons | Central West Virginia Regional Airport AuthorityCharleston, West Virginia | 2015 | Study materials |
Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.
Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.