Concrete barrier-wall construction in the Wolf Creek Dam embankment on May 2, 2012.

US Army Corps of Engineers · 2013

Wolf Creek Dam — karst-foundation cutoff wall

A deep concrete barrier and associated grouting addressed seepage through the dam’s karst foundation. USACE documents completion and project scope.

Dams and leveesSeepage and internal erosionRock slopes and foundations
Annotated aerial photograph of the completed Prototype Hanford Barrier in August 1994.

US Department of Energy / PNNL · 2024

Prototype Hanford Barrier — long-term infiltration control

Long-term monitoring examines an evapotranspiration-capillary barrier intended to limit infiltration into waste. The annual report also discusses side-slope edge effects.

Contaminated ground and waste barriersSeepage and internal erosionMonitoring and observational design
Aerial view of the Port of Brisbane and adjoining airport in 2015.

Port of Brisbane · 2009

Port of Brisbane — vacuum consolidation beside a marine park

A reclamation trial combined vacuum preloading and vertical drainage in soft dredged mud and underlying clay. A cutoff isolated permeable layers, while stability at the adjacent marine park constrained surcharge filling.

Ground improvementSettlement and consolidationSeepage and internal erosion
Aerial view of the raised San Vicente Dam and reservoir in San Diego County.

San Diego County Water Authority · 2014

San Vicente Dam raise — rock preparation and RCC interface

The existing concrete dam was raised using roller-compacted concrete. Owner documents connect excavation to competent rock, treatment of localized poor material and seepage control with the enlarged structure.

Rock slopes and foundationsDams and leveesSeepage and internal erosion
Aerial view of the Isabella Dam Safety Modification Project on 14 September 2022.

US Army Corps of Engineers · 2023

Isabella Dam modifications — seismic, seepage and spillway risk

The main and auxiliary dams were modified to address combined seismic, seepage and flood-passage concerns. Owner records describe dam raises, downstream buttress work, filters, drainage and major spillway excavation.

Dams and leveesSeepage and internal erosionEarthquakes and liquefaction
East Branch Clarion River Lake and Dam near Wilcox, Pennsylvania.

US Army Corps of Engineers · 2020

East Branch Dam — cutoff-wall construction and verification

A dam-repair programme installed a cutoff wall to reduce foundation seepage. USACE reports the contract and return toward normal operations; the technical literature discusses wall verification drilling.

Dams and leveesSeepage and internal erosionGround improvement
Aerial view of construction equipment along the crest of Clearwater Lake Dam in Missouri.

US Army Corps of Engineers · 2011

Clearwater Dam — karst pretreatment and a hanging cutoff

A sinkhole prompted foundation exploration and grouting before construction of a deep seepage cutoff. The owner explains why treating solution-enlarged fractures was necessary for slurry-supported excavation.

Dams and leveesSeepage and internal erosionRock slopes and foundations
Seepage east of and below the Mosul Dam spillway.

Iraq Ministry of Water Resources · 2019

Mosul Dam — maintenance grouting in soluble foundations

The dam overlies soluble limestone and gypsum. A rehabilitation programme strengthened maintenance grouting, equipment and instrumentation; continuing operation depends on sustained foundation management.

Dams and leveesSeepage and internal erosionRock slopes and foundations
Glen Canyon Dam under construction in 1962.

US Bureau of Reclamation · 1966

Glen Canyon Dam — sandstone abutments and controlled seepage

The high concrete dam required canyon-wall stabilization, river diversion and excavation to sandstone bedrock. Reclamation describes rock bolts, seepage measurement and the geological basis of the site selection.

Rock slopes and foundationsDams and leveesSeepage and internal erosion
Aerial view of construction at the IHNC–Lake Borgne Surge Barrier in eastern New Orleans.

Flood Protection Authority East / USACE · 2013

Lake Borgne surge barrier — pile-supported flood protection

The barrier combines a long pile-supported wall with navigation gates and levee connections. The geotechnical consultant describes capacity, settlement, global stability and temporary-works analyses in soft coastal deposits.

Piles and drilled shaftsLateral foundations and interactionCoastal and offshore foundations
The Vajont landslide in 1963.

Historic reservoir project / Italian public investigation · 1963

Vajont reservoir — rockslide, groundwater and observational decisions

The reservoir disaster involved a large pre-existing rockslide and rapid displacement of reservoir water. Geological researchers emphasize the complex shear zone and the influence of groundwater and reservoir operations.

Soil slopes and landslidesRock slopes and foundationsDams and levees
Ruins of Malpasset Dam photographed in 2007.

Historic Malpasset water-supply project · 1959

Malpasset Dam — abutment wedge failure and uplift

The arch dam failed after instability developed in its rock foundation. The French dam committee and government accident record describe the role of discontinuity geometry, uplift and stress-dependent drainage.

Rock slopes and foundationsDams and leveesSeepage and internal erosion
View into the Love Canal containment area in 2012.

US EPA / New York State Department of Environmental Conservation · 1985

Love Canal — containment cap and barrier drainage

The remedy contains waste beneath a cap and intercepts contaminated groundwater for treatment. EPA records describe the expanded synthetic cover, barrier drains and continuing inspection programme.

Contaminated ground and waste barriersSeepage and internal erosionDewatering and groundwater
The entrance to the Svalbard Global Seed Vault in February 2020, after the 2016–2019 upgrade period. The photograph shows the actual facility; buried tunnel details are documented by the linked owner sources.

Norwegian Ministry of Agriculture and Food / Statsbygg · 2019

Svalbard Seed Vault — tunnel waterproofing and frozen ground

The Seed Vault upgrade replaced its access tunnel with a watertight concrete structure and moved heat-producing services. The construction account includes artificial ground freezing to support the replacement works.

Permafrost and cold regionsTunnels and underground worksGround improvement
Rocky Flats in 2007 after removal of the former industrial buildings. The broad site view does not establish the location or condition of individual landfill-cover layers or groundwater treatment cells.

U.S. Department of Energy, Office of Legacy Management · 2026

Rocky Flats — engineered covers and long-term groundwater care

The remediated site retains engineered landfill covers, groundwater collection/treatment systems and long-term inspections. Public surveillance records support a capstone on containment performance after closure.

Contaminated ground and waste barriersSeepage and internal erosionSoil slopes and landslides

From project evidence to a design study

Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.

Topic coverage

Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.