Bowman Road Bridge — reinforced-soil abutments
The first production GRS integrated bridge system used reinforced-soil abutments. FHWA publishes a worked Bowman Road design and subsequent performance discussion.
Foundation Design · Cases
Documented projects, design decisions and lessons for engineering practice and capstone studies.
43 of 117 project case studies
The first production GRS integrated bridge system used reinforced-soil abutments. FHWA publishes a worked Bowman Road design and subsequent performance discussion.
Rapid highway reconstruction over soft lacustrine soils used geofoam, lime-cement columns, vertical drains, surcharge and staged MSE construction. UDOT reports ten-year performance.
UDOT used geofoam blocks for the ramp connecting West Davis Highway to southbound I-15, with existing transport infrastructure constraining allowable settlement.
This design-build highway case documents drilled-shaft assessment using crosshole sonic logging and pile-integrity tests, including construction anomalies.
Four bridge retrofits used hollow-core bar micropiles under limited headroom after deterioration of exposed precast piles. The submitted case includes proof and verification tests.
A highway embankment over organic clay used vertical drains, surcharge and staged filling, with remote monitoring of pore pressure and settlement.
The arena foundation study compared deep foundations with spread footings on improved ground. Test sections supported the selected compaction and replacement approach.
Project research documents deep mixing in marine clay at Bird Island Flats and Fort Point Channel and the control of excavation-induced movements.
The bored-tunnel replacement passed beneath downtown Seattle. Owner material includes geology/soils assessment, procurement information and completion history.
A deep concrete barrier and associated grouting addressed seepage through the dam’s karst foundation. USACE documents completion and project scope.
A staged rehabilitation treated foundation seepage and auxiliary-dam risks using grouting, a deep cutoff wall and a roller-compacted-concrete berm.
The rehabilitation combined cutoff walls, culvert replacements and embankment armoring around Lake Okeechobee. USACE provides a completion summary and project update.
The auxiliary spillway required major rock excavation and preparation of the control-structure foundation before concrete placement.
Recovery rebuilt the main spillway and added a secant pile wall, splashpad and buttress at the emergency spillway after the 2017 incident.
The navigation replacement became operational in 2018 after a long construction programme. USACE publishes project-control updates and completion material.
After the 2020 fire, CDOT compared rockfall mitigation using risk and benefit-cost analysis. Subsequent debris flows exceeded some installed protection capacities.
Rockslides near Ocoee Dam 2 required rock removal, bolting and stabilization while weather and difficult access affected the reopening programme.
The campus system uses closed-loop borefields to exchange heat with the ground. University material describes the two-field arrangement and staged conversion.
Twelve embankment test sections compared air-convection shoulder geometry and rock classes over thaw-unstable permafrost near milepost 219.
After a rainfall-triggered slide, ALDOT selected two bridges across the unstable area rather than reconstructing the road on the moving embankment.
Flood damage and channel migration prompted comparison of replacement spans and erosion protection at the County Road 91 crossing.
Following Hurricane Michael, roadway reconstruction incorporated articulated concrete blocks over filter fabric and bedding to reduce recurring embankment erosion.
After the 2019 flood damaged the road embankment, Iowa DOT selected anchored concrete-block matting and evaluated recurring-damage economics.
The integrated resort was constructed on reclaimed waterfront land. The foundation contractors describe bored piling and advance removal of a buried seawall within a tightly constrained site.
| Title | Type | Owner / location | Year | Access |
|---|---|---|---|---|
| Bowman Road Bridge — reinforced-soil abutments | Design and construction | Defiance CountyDefiance County, Ohio | 2005 | Original documents |
| I-15 reconstruction — soft-ground embankments and geofoam | Design and construction | Utah Department of TransportationSalt Lake City, Utah | 2001 | Study materials |
| West Davis Highway ramp — lightweight fill beside live transport | Design and construction | Utah Department of TransportationFarmington, Utah | 2023 | Study materials |
| Virginia Route 288 — drilled-shaft quality evaluation | Construction quality and testing | Virginia Department of TransportationRichmond region, Virginia | 2004 | Study materials |
| New Jersey Turnpike bridges — micropile underpinning | Rehabilitation | New Jersey highway agencies; see sourceNew Jersey | 2008 | Study materials |
| US 14 near Nicollet — preload and vertical drains | Design and construction | Minnesota Department of TransportationNicollet, Minnesota | 2016 | Study materials |
| Prudential Center — shallow foundations after improvement | Redevelopment | New Jersey DevilsNewark, New Jersey | 2006 | Study materials |
| Boston Central Artery/Tunnel — deep mixing and ground movement | Design and construction | Massachusetts highway agenciesBoston, Massachusetts | 2006 | Study materials |
| Seattle SR 99 tunnel — soft-ground tunnelling and settlement | Design and construction | Washington State Department of TransportationSeattle, Washington | 2019 | Study materials |
| Wolf Creek Dam — karst-foundation cutoff wall | Rehabilitation | US Army Corps of EngineersJamestown, Kentucky | 2013 | Study materials |
| Center Hill Dam — grouting, cutoff wall and stabilizing berm | Rehabilitation | US Army Corps of EngineersDeKalb County, Tennessee | 2020 | Study materials |
| Herbert Hoover Dike — seepage barriers and structure replacement | Rehabilitation | US Army Corps of EngineersLake Okeechobee, Florida | 2023 | Original documents |
| Folsom auxiliary spillway — rock excavation and foundation preparation | Design and construction | USACE / Bureau of ReclamationFolsom, California | 2017 | Study materials |
| Oroville spillway recovery — erosion-resistant foundation reconstruction | Rehabilitation | California Department of Water ResourcesOroville, California | 2018 | Study materials |
| Olmsted Locks and Dam — marine construction and project controls | Design and construction | US Army Corps of EngineersOhio River, Illinois–Kentucky | 2018 | Study materials |
| I-70 Grizzly Creek — post-fire rockfall risk and betterment | Rehabilitation | Colorado Department of TransportationGlenwood Canyon, Colorado | 2021 | Original documents |
| US 64 Ocoee Gorge — emergency rockslide stabilization | Rehabilitation | Tennessee Department of TransportationPolk County, Tennessee | 2010 | Study materials |
| Ball State University — campus ground-source borefields | Design and construction | Ball State UniversityMuncie, Indiana | 2012 | Study materials |
| Dalton Highway MP 209–222 — air-convection embankment trial | Field demonstration | Alaska Department of Transportation and Public FacilitiesAlaska | 2022 | Study materials |
| US 231, Lacey Springs — bridging a moving landslide | Rehabilitation | Alabama Department of TransportationLacey Springs, Alabama | 2020 | Original documents |
| Beaver Dam Wash Bridge — scour-resistant replacement | Rehabilitation | Mohave County Public WorksMohave County, Arizona | 2005 | Original documents |
| US 98, Florida — coastal roadway revetment | Rehabilitation | Florida Department of TransportationFlorida Panhandle | 2018 | Original documents |
| US 34, Iowa — flood-resistant embankment matting | Rehabilitation | Iowa Department of TransportationMills County, Iowa | 2021 | Original documents |
| Marina Bay Sands — deep foundations on reclaimed ground | Design, construction and performance | Marina Bay SandsMarina Bay, Singapore | 2010 | Study materials |
Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.
Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.