Foundation Design · Cases

Find Engineering Cases

Documented projects, design decisions and lessons for engineering practice and capstone studies.

Owner, location & access
Clear filters

20 of 117 project case studies

Aerial view of the completed Woodrow Wilson Memorial Bridge over the Potomac River, March 2012.

Virginia DOT / Maryland State Highway Administration · 2008

Woodrow Wilson Bridge — foundation selection and testing

Technical project papers describe foundation alternatives and the new bridge foundations, including seismic soil–structure interaction and scour considerations.

Piles and drilled shaftsLateral foundations and interactionSite investigation
Microcamera photograph of defective concrete inside a Route 288 drilled shaft, from the project evaluation paper’s Figure 9. This is the actual shaft inspection, rather than an exterior bridge view.

Virginia Department of Transportation · 2004

Virginia Route 288 — drilled-shaft quality evaluation

This design-build highway case documents drilled-shaft assessment using crosshole sonic logging and pile-integrity tests, including construction anomalies.

Piles and drilled shaftsSite investigationMonitoring and observational design
Production micropiles installed under limited headroom at one of the New Jersey Turnpike bridge retrofits. Original Figure 3 from the project authors’ 2008 paper.

New Jersey highway agencies; see source · 2008

New Jersey Turnpike bridges — micropile underpinning

Four bridge retrofits used hollow-core bar micropiles under limited headroom after deterioration of exposed precast piles. The submitted case includes proof and verification tests.

Piles and drilled shaftsScour and erosion protectionMonitoring and observational design
The completed US 231 bridges at Lacey Springs span the unstable slope, shown in the FHWA case study’s Figure 3.

Alabama Department of Transportation · 2020

US 231, Lacey Springs — bridging a moving landslide

After a rainfall-triggered slide, ALDOT selected two bridges across the unstable area rather than reconstructing the road on the moving embankment.

Soil slopes and landslidesPiles and drilled shaftsLateral foundations and interaction
Burj Khalifa in Dubai.

Emaar Properties · 2010

Burj Khalifa — piled-raft settlement design

The tower uses a piled raft in weak sedimentary rock. The foundation designer publishes an analysis process linking ground characterization, trial pile testing and settlement predictions for super-tall towers.

Piles and drilled shaftsShallow foundationsSettlement and consolidation
Construction of the Marina Bay Sands resort in Singapore.

Marina Bay Sands · 2010

Marina Bay Sands — deep foundations on reclaimed ground

The integrated resort was constructed on reclaimed waterfront land. The foundation contractors describe bored piling and advance removal of a buried seawall within a tightly constrained site.

Piles and drilled shaftsExcavation supportDewatering and groundwater
The Millau Viaduct during construction.

Compagnie Eiffage du Viaduc de Millau · 2004

Millau Viaduct — rock foundations and observational control

Very tall bridge piers transfer load through large shaft-and-raft foundations in limestone and marl. The geotechnical authors report measured foundation movement and the observational design strategy.

Rock slopes and foundationsPiles and drilled shaftsSettlement and consolidation
Aerial view of construction at the IHNC–Lake Borgne Surge Barrier in eastern New Orleans.

Flood Protection Authority East / USACE · 2013

Lake Borgne surge barrier — pile-supported flood protection

The barrier combines a long pile-supported wall with navigation gates and levee connections. The geotechnical consultant describes capacity, settlement, global stability and temporary-works analyses in soft coastal deposits.

Piles and drilled shaftsLateral foundations and interactionCoastal and offshore foundations
The West Closure Complex during its 2023 annual operational testing.

US Army Corps of Engineers · 2011

West Closure Complex — foundations on soft deltaic deposits

The gate and pumping complex is founded in soft, compressible deltaic deposits. USACE authors describe exploration, laboratory characterization and pile testing used to develop design strength profiles.

Piles and drilled shaftsLaboratory testing and parametersSite investigation
A vertical support member of the Trans-Alaska Pipeline topped by two heat-pipe radiators.

Alyeska Pipeline Service Company · 2022

Trans-Alaska Pipeline — thermally stabilized supports in permafrost

The pipeline uses elevated supports where thaw-sensitive permafrost would be disturbed by warm oil. Operator and state-geology sources describe thermal support members, heat-pipe monitoring and maintenance.

Permafrost and cold regionsPiles and drilled shaftsMonitoring and observational design
Aerial view of the Port of Anchorage, now the Don Young Port of Alaska.

Don Young Port of Alaska · 2020

Port of Alaska — test piles and seismic waterfront foundations

Modernization studies used offshore investigation and a test-pile programme to examine drivability, capacity and underwater noise. The petroleum/cement terminal team also characterized cyclic behavior and soil–structure interaction.

Piles and drilled shaftsLateral foundations and interactionLaboratory testing and parameters
The new Cannon Street entrance to Bank station in February 2023.

London Underground · 2023

Bank station upgrade — tunnelling through existing pile zones

The capacity upgrade required new tunnels beside operating infrastructure and existing building piles. The designer describes staged building-impact assessment and a load-transfer solution that retained foundation reuse options.

Tunnels and underground worksPiles and drilled shaftsLateral foundations and interaction
Sutong Bridge during construction. The image shows the actual crossing; detailed shaft groups, pile-cap geometry and scour protection are described in the project engineering papers.

Sutong Bridge project authorities · 2008

Sutong Bridge — deep pile groups and riverbed scour protection

The main pylons use large groups of long drilled shafts in deep water and soft ground. Project papers connect testing, pile-group analysis, post-grouting, cofferdam construction and permanent scour protection.

Piles and drilled shaftsLateral foundations and interactionScour and erosion protection

From project evidence to a design study

Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.

Topic coverage

Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.