Foundation Design · Cases

Find Engineering Cases

Documented projects, design decisions and lessons for engineering practice and capstone studies.

Owner, location & access
Clear filters

17 of 117 project case studies

Aerial view of the completed Woodrow Wilson Memorial Bridge over the Potomac River, March 2012.

Virginia DOT / Maryland State Highway Administration · 2008

Woodrow Wilson Bridge — foundation selection and testing

Technical project papers describe foundation alternatives and the new bridge foundations, including seismic soil–structure interaction and scour considerations.

Piles and drilled shaftsLateral foundations and interactionSite investigation
Aerial photograph of liquefaction at QEII Park and its surroundings on 11 March 2011. This records the site context before the later ground-improvement trials, not the trial construction.

New Zealand building ministry and trial partners · 2012

Canterbury residential ground-improvement trials

The 2012 trials compared shallow rafts, mixing columns, a perimeter curtain and densification approaches to support residential foundation repair and rebuilding.

Ground improvementEarthquakes and liquefactionShallow foundations
Palm Jumeirah viewed from a helicopter in May 2008.

Nakheel · 2006

Palm Jumeirah — densification of reclaimed sand

The artificial island’s reclaimed sand was treated by vibrocompaction before infrastructure construction. The project’s visitor centre explains the working sequence and its role in controlling settlement and liquefaction susceptibility.

Ground improvementCoastal and offshore foundationsEarthquakes and liquefaction
Aerial view of Calaveras Reservoir during reconstruction of the dam.

San Francisco Public Utilities Commission · 2019

Calaveras Dam replacement — seismic foundations and unexpected landslides

Replacement of a seismically vulnerable dam encountered an additional ancient landslide during abutment excavation. Public environmental and budget records document supplemental investigation, design revisions and delivery consequences.

Dams and leveesEarthquakes and liquefactionSoil slopes and landslides
Aerial view of the Isabella Dam Safety Modification Project on 14 September 2022.

US Army Corps of Engineers · 2023

Isabella Dam modifications — seismic, seepage and spillway risk

The main and auxiliary dams were modified to address combined seismic, seepage and flood-passage concerns. Owner records describe dam raises, downstream buttress work, filters, drainage and major spillway excavation.

Dams and leveesSeepage and internal erosionEarthquakes and liquefaction
Interior of the Marmaray tunnel project in 2012.

Republic of Türkiye transport authorities · 2013

Marmaray crossing — immersed-tunnel foundations in seismic ground

The immersed crossing combined a gravel foundation, under-base grouting and treatment of liquefiable deposits. A project paper explains element connections and the transition to adjacent bored tunnels under severe seismic demands.

Tunnels and underground worksEarthquakes and liquefactionGround improvement
The Asian entrance of the Eurasia Tunnel in Istanbul.

Eurasia Tunnel concession / transport authority · 2016

Eurasia Tunnel — high-pressure mixed-ground TBM crossing

The road tunnel passes through rock and marine sediments at high water pressure. The designers describe slurry-shield excavation, specialized lining details and seismic joints near changes in ground stiffness.

Tunnels and underground worksEarthquakes and liquefactionDewatering and groundwater
The Turnagain Heights landslide after the 1964 Alaska earthquake.

USGS / Alaska geological investigation · 1964

Turnagain Heights — earthquake-triggered bluff failure

The earthquake triggered destructive ground movement in bluffs underlain by the Bootlegger Cove Formation. USGS later characterized individual facies to examine their roles in the landslide.

Soil slopes and landslidesEarthquakes and liquefactionExpansive, collapsible and organic soils
Buildings affected by soil liquefaction during the 1964 Niigata earthquake.

Japanese earthquake investigators · 1964

Niigata earthquake — contrasting liquefied and non-liquefied sites

Published investigations compare sites that did and did not liquefy, linking penetration tests, recovered sand samples and cyclic strength. Building tilting demonstrates the importance of ground response even when the superstructure remains comparatively intact.

Earthquakes and liquefactionLaboratory testing and parametersSite investigation
Liquefaction damage in Minatojima-Nakamachi on Kobe’s Port Island on 17 January 1995.

Port of Kobe / Japanese port researchers · 1995

Kobe Port — quay-wall displacement during liquefaction

Many caisson quay walls moved seaward during the 1995 earthquake. Port researchers studied the combined contributions of inertia and excess pore pressure beneath and behind the walls.

Earthquakes and liquefactionRetaining walls and anchorsCoastal and offshore foundations
Aerial view of the Port of Anchorage, now the Don Young Port of Alaska.

Don Young Port of Alaska · 2020

Port of Alaska — test piles and seismic waterfront foundations

Modernization studies used offshore investigation and a test-pile programme to examine drivability, capacity and underwater noise. The petroleum/cement terminal team also characterized cyclic behavior and soil–structure interaction.

Piles and drilled shaftsLateral foundations and interactionLaboratory testing and parameters
The Osman Gazi Bridge across Izmit Bay. The buried and submerged foundation details are documented in the linked design and construction sources.

Gebze–Orhangazi–Izmir motorway project · 2016

Osman Gazi Bridge — seismic caissons on gravel beds

The suspension bridge combines offshore caisson foundations with improved ground and a gravel interface intended to accommodate extreme seismic movement. Published accounts describe soil–structure interaction and marine installation.

Lateral foundations and interactionEarthquakes and liquefactionGround improvement

From project evidence to a design study

Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.

Topic coverage

Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.