Satellite view of Kansai International Airport and its reclaimed offshore island works.

Kansai Airports · 2025

Kansai International Airport — reclamation and long-term settlement

An offshore airport on deep marine deposits combines accelerated consolidation with ongoing settlement observation and adjustable building supports. The operator publishes measured island subsidence and its mitigation approach.

Settlement and consolidationGround improvementExpansive, collapsible and organic soils
The Millau Viaduct during construction.

Compagnie Eiffage du Viaduc de Millau · 2004

Millau Viaduct — rock foundations and observational control

Very tall bridge piers transfer load through large shaft-and-raft foundations in limestone and marl. The geotechnical authors report measured foundation movement and the observational design strategy.

Rock slopes and foundationsPiles and drilled shaftsSettlement and consolidation
East Branch Clarion River Lake and Dam near Wilcox, Pennsylvania.

US Army Corps of Engineers · 2020

East Branch Dam — cutoff-wall construction and verification

A dam-repair programme installed a cutoff wall to reduce foundation seepage. USACE reports the contract and return toward normal operations; the technical literature discusses wall verification drilling.

Dams and leveesSeepage and internal erosionGround improvement
Seepage east of and below the Mosul Dam spillway.

Iraq Ministry of Water Resources · 2019

Mosul Dam — maintenance grouting in soluble foundations

The dam overlies soluble limestone and gypsum. A rehabilitation programme strengthened maintenance grouting, equipment and instrumentation; continuing operation depends on sustained foundation management.

Dams and leveesSeepage and internal erosionRock slopes and foundations
Aerial view of construction at the IHNC–Lake Borgne Surge Barrier in eastern New Orleans.

Flood Protection Authority East / USACE · 2013

Lake Borgne surge barrier — pile-supported flood protection

The barrier combines a long pile-supported wall with navigation gates and levee connections. The geotechnical consultant describes capacity, settlement, global stability and temporary-works analyses in soft coastal deposits.

Piles and drilled shaftsLateral foundations and interactionCoastal and offshore foundations
Faido crossover area in the Gotthard Base Tunnel during construction in 2014.

AlpTransit Gotthard · 2016

Gotthard Base Tunnel — squeezing rock and adaptive support

Deep tunnel sections encountered squeezing rock and strongly variable geological behavior. The Swiss geotechnical society’s project history explains both anticipated and unexpected support challenges at Sedrun and Faido.

Tunnels and underground worksRock slopes and foundationsSite investigation
Thames Tideway Tunnel construction at Nine Elms, London.

Tideway · 2022

Thames Tideway Tunnel — variable geology and deep shafts

The sewer tunnel crosses the London Basin sequence from clay into water-bearing chalk. Project engineers explain how geological observations and groundwater pressure influenced excavation methods and construction performance.

Tunnels and underground worksDewatering and groundwaterSite investigation
Construction of the future 86th Street station in November 2013.

Metropolitan Transportation Authority · 2017

Second Avenue Subway Phase 1 — ground freezing at a TBM launch

Unexpected poor ground near the east running-tunnel launch required a revised sequence. The construction manager describes soil freezing while the TBM first advanced through the western alignment.

Tunnels and underground worksGround improvementMonitoring and observational design
Excavation beneath Northern Boulevard in Queens in December 2012.

Metropolitan Transportation Authority · 2013

East Side Access — frozen support beneath Northern Boulevard

A short mined connection beneath active transport infrastructure used a frozen soil arch for temporary support and groundwater cutoff. The project sources distinguish local freezing from the wider East Side Access tunnel programme.

Tunnels and underground worksGround improvementDewatering and groundwater
City Rail Link construction on Albert Street in Auckland.

City Rail Link Limited · 2023

Auckland City Rail Link — ground models and settlement baselines

The urban rail link traverses weak rock, younger sediments, volcanic material and reclamation. Project engineers describe how phased investigations and a shared three-dimensional ground model informed procurement and risk allocation.

Tunnels and underground worksSite investigationMonitoring and observational design
A vertical support member of the Trans-Alaska Pipeline topped by two heat-pipe radiators.

Alyeska Pipeline Service Company · 2022

Trans-Alaska Pipeline — thermally stabilized supports in permafrost

The pipeline uses elevated supports where thaw-sensitive permafrost would be disturbed by warm oil. Operator and state-geology sources describe thermal support members, heat-pipe monitoring and maintenance.

Permafrost and cold regionsPiles and drilled shaftsMonitoring and observational design
The Vajont landslide in 1963.

Historic reservoir project / Italian public investigation · 1963

Vajont reservoir — rockslide, groundwater and observational decisions

The reservoir disaster involved a large pre-existing rockslide and rapid displacement of reservoir water. Geological researchers emphasize the complex shear zone and the influence of groundwater and reservoir operations.

Soil slopes and landslidesRock slopes and foundationsDams and levees
View into the Love Canal containment area in 2012.

US EPA / New York State Department of Environmental Conservation · 1985

Love Canal — containment cap and barrier drainage

The remedy contains waste beneath a cap and intercepts contaminated groundwater for treatment. EPA records describe the expanded synthetic cover, barrier drains and continuing inspection programme.

Contaminated ground and waste barriersSeepage and internal erosionDewatering and groundwater
View from One New Change toward St Paul’s Cathedral.

Land Securities · 2010

One New Change — basement effects on St Paul’s groundwater

Redevelopment beside St Paul’s Cathedral required assessment of groundwater changes in shallow deposits supporting the historic structure. The designer describes conceptual and numerical groundwater modeling followed by construction monitoring.

Excavation supportDewatering and groundwaterShallow foundations
The Nicoll Highway collapse site photographed in April 2024.

Singapore Land Transport Authority / Committee of Inquiry · 2004

Nicoll Highway collapse — excavation design and monitoring decisions

The official inquiry identified errors in retaining-wall and strut-connection design and failures to respond adequately to warning signs. The case joins ground-model selection, temporary-structure detailing and construction governance.

Excavation supportRetaining walls and anchorsMonitoring and observational design
The new Cannon Street entrance to Bank station in February 2023.

London Underground · 2023

Bank station upgrade — tunnelling through existing pile zones

The capacity upgrade required new tunnels beside operating infrastructure and existing building piles. The designer describes staged building-impact assessment and a load-transfer solution that retained foundation reuse options.

Tunnels and underground worksPiles and drilled shaftsLateral foundations and interaction
The ETH Hönggerberg campus, where the anergy grid exchanges heat with borehole fields. This site-context photograph does not show the buried HC4 boreholes.

ETH Zurich · 2025

ETH Hönggerberg — seasonal borehole heat storage

The campus anergy grid balances heating and cooling through buried borehole fields. Its documented HC4 expansion provides a practical study of thermal interference, drilling access and staged commissioning.

Ground-source energySite investigationDewatering and groundwater

From project evidence to a design study

Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.

Topic coverage

Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.