Foundation Design · Cases

Find Engineering Cases

Documented projects, design decisions and lessons for engineering practice and capstone studies.

Owner, location & access
Clear filters

32 of 117 project case studies

Aerial view of the completed Woodrow Wilson Memorial Bridge over the Potomac River, March 2012.

Virginia DOT / Maryland State Highway Administration · 2008

Woodrow Wilson Bridge — foundation selection and testing

Technical project papers describe foundation alternatives and the new bridge foundations, including seismic soil–structure interaction and scour considerations.

Piles and drilled shaftsLateral foundations and interactionSite investigation
Microcamera photograph of defective concrete inside a Route 288 drilled shaft, from the project evaluation paper’s Figure 9. This is the actual shaft inspection, rather than an exterior bridge view.

Virginia Department of Transportation · 2004

Virginia Route 288 — drilled-shaft quality evaluation

This design-build highway case documents drilled-shaft assessment using crosshole sonic logging and pile-integrity tests, including construction anomalies.

Piles and drilled shaftsSite investigationMonitoring and observational design
Aerial photograph of the completed soil-nailed walls along River Road in Pima County, Arizona. The original Google attribution remains in the image.

Pima County Department of Transportation · 2004

River Road, Tucson — tall soil-nailed cuts

Road widening beneath developed bluffs used tall soil-nailed walls. Loose seams and constrained investigation access required construction responses.

Retaining walls and anchorsExcavation supportSite investigation
Observed pavement distortion on KY 499 in Estill County, Kentucky, documented in the swelling investigation report.

Kentucky Transportation Cabinet / University of Kentucky · 2005

KY 499, Estill County — pavement swelling investigation

Field and laboratory work investigated heave of a relatively young pavement over compacted clay shale and distinguished wetting expansion from a suspected sulfate reaction.

Expansive, collapsible and organic soilsLaboratory testing and parametersEarthworks and pavement subgrades
The SH 6 study section in the original expansive-subgrade investigation, reproduced from the scanned Figure 6 photograph. The source scan has limited image quality.

Texas Department of Transportation / Texas A&M · 1996

Texas SH 6 and SH 21 — expansive-subgrade distress

A TxDOT-funded project investigated swelling clay beneath distressed pavement sections and evaluated characterization and stabilization alternatives.

Expansive, collapsible and organic soilsLaboratory testing and parametersEarthworks and pavement subgrades
Historical aerial photograph of the enclosed Changi East slurry pond before reclamation.

Singapore reclamation authorities · 2005

Changi East reclamation — instrumented vertical-drain design

The reclamation programme used prefabricated vertical drains to accelerate consolidation of marine clay. Its investigators publish pilot trials, specialized testing and interpretation of settlement and pore-pressure records.

Settlement and consolidationGround improvementLaboratory testing and parameters
Aerial view of Calaveras Reservoir during reconstruction of the dam.

San Francisco Public Utilities Commission · 2019

Calaveras Dam replacement — seismic foundations and unexpected landslides

Replacement of a seismically vulnerable dam encountered an additional ancient landslide during abutment excavation. Public environmental and budget records document supplemental investigation, design revisions and delivery consequences.

Dams and leveesEarthquakes and liquefactionSoil slopes and landslides
Glen Canyon Dam under construction in 1962.

US Bureau of Reclamation · 1966

Glen Canyon Dam — sandstone abutments and controlled seepage

The high concrete dam required canyon-wall stabilization, river diversion and excavation to sandstone bedrock. Reclamation describes rock bolts, seepage measurement and the geological basis of the site selection.

Rock slopes and foundationsDams and leveesSeepage and internal erosion
The West Closure Complex during its 2023 annual operational testing.

US Army Corps of Engineers · 2011

West Closure Complex — foundations on soft deltaic deposits

The gate and pumping complex is founded in soft, compressible deltaic deposits. USACE authors describe exploration, laboratory characterization and pile testing used to develop design strength profiles.

Piles and drilled shaftsLaboratory testing and parametersSite investigation
Faido crossover area in the Gotthard Base Tunnel during construction in 2014.

AlpTransit Gotthard · 2016

Gotthard Base Tunnel — squeezing rock and adaptive support

Deep tunnel sections encountered squeezing rock and strongly variable geological behavior. The Swiss geotechnical society’s project history explains both anticipated and unexpected support challenges at Sedrun and Faido.

Tunnels and underground worksRock slopes and foundationsSite investigation
The Channel Tunnel construction site in May 1991.

Eurotunnel · 1994

Channel Tunnel — geological alignment and water-pressure control

The alignment sought low-permeability marly chalk while accommodating more fractured ground on the French side. Project geologists describe how marine seismic surveys and boreholes informed route selection and machine requirements.

Tunnels and underground worksRock slopes and foundationsSite investigation
The Asian entrance of the Eurasia Tunnel in Istanbul.

Eurasia Tunnel concession / transport authority · 2016

Eurasia Tunnel — high-pressure mixed-ground TBM crossing

The road tunnel passes through rock and marine sediments at high water pressure. The designers describe slurry-shield excavation, specialized lining details and seismic joints near changes in ground stiffness.

Tunnels and underground worksEarthquakes and liquefactionDewatering and groundwater
Thames Tideway Tunnel construction at Nine Elms, London.

Tideway · 2022

Thames Tideway Tunnel — variable geology and deep shafts

The sewer tunnel crosses the London Basin sequence from clay into water-bearing chalk. Project engineers explain how geological observations and groundwater pressure influenced excavation methods and construction performance.

Tunnels and underground worksDewatering and groundwaterSite investigation
The northbound entrance to Kuala Lumpur’s SMART Tunnel.

Department of Irrigation and Drainage / Malaysian Highway Authority · 2007

SMART Tunnel — tunnelling through urban karst

The combined stormwater and road tunnel passes through highly irregular limestone and overlying deposits. The builder and ground-treatment contractor describe slurry-shield excavation, grouting and sinkhole-management challenges.

Tunnels and underground worksRock slopes and foundationsDewatering and groundwater
City Rail Link construction on Albert Street in Auckland.

City Rail Link Limited · 2023

Auckland City Rail Link — ground models and settlement baselines

The urban rail link traverses weak rock, younger sediments, volcanic material and reclamation. Project engineers describe how phased investigations and a shared three-dimensional ground model informed procurement and risk allocation.

Tunnels and underground worksSite investigationMonitoring and observational design
Ruins of Malpasset Dam photographed in 2007.

Historic Malpasset water-supply project · 1959

Malpasset Dam — abutment wedge failure and uplift

The arch dam failed after instability developed in its rock foundation. The French dam committee and government accident record describe the role of discontinuity geometry, uplift and stress-dependent drainage.

Rock slopes and foundationsDams and leveesSeepage and internal erosion
Concrete ruins at the St.

Historic Los Angeles water-supply project · 1928

St. Francis Dam — investigation evidence and foundation reassessment

The 1928 collapse prompted an official investigation and later reassessments of geology and foundation behavior. The records make a useful exercise in distinguishing contemporary findings from subsequent hypotheses.

Rock slopes and foundationsDams and leveesExpansive, collapsible and organic soils

From project evidence to a design study

Each case separates documented project decisions and available records from a suggested capstone exercise. Missing final designs, costs, schedules or completion records are identified. A teaching exercise may require additional assumptions, site investigation or instructor-supplied inputs.

Topic coverage

Projects may address several topics. Counts below represent relevant project records, not independent examples for every method.